40 men can complete a work in 15 days. Five days after they started working, 10 more men joined them. In how many days will the total work be completed?

  1. A
    13
  2. B
    12
  3. C
    14
  4. D
    11

Solution & Step-by-step Explanation

Let the efficiency of 1 man be 1 unit/day.
Total work = 40×15=600 units.

Work done by 40 men in the first 5 days:

Work Done=40×5=200 units
Remaining work:

Remaining Work=600−200=400 units
Now, 10 more men join, so total men = 40+10=50 men.
Time taken by 50 men to finish the remaining work:

Remaining Days=
50
400

=8 days
Total days to complete the work:

Total Days=5 days (initial)+8 days (remaining)=13 days

Practice this question

Try it yourself before checking the explanation above.

40 men can complete a work in 15 days. Five days after they started working, 10 more men joined them. In how many days will the total work be completed?
A
13
B
12
C
14
D
11

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion