HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
2 attempts0% success rate1 mark

A and B can complete a task in 40 days and 16 days respectively. A started the task alone and then after 12 days B joined him till the completion of the task. How long did the task last after B joined the task?

  1. A
    8 days
  2. B
    6 days
  3. C
    14 days
  4. D
    12 days

Solution & Step-by-step Explanation

Let the total work be the LCM of 40 and 16, which is 80 units.
Efficiency of A=
40
80

=2 units/day

Efficiency of B=
16
80

=5 units/day

A worked alone for 12 days:

Work done by A in 12 days=2×12=24 units
Remaining work=80−24=56 units
Now B joins A, so their combined efficiency is:

Combined efficiency=2+5=7 units/day
The time taken by both to complete the remaining work after B joined:

Time=
Combined efficiency
Remaining work

=
7
56

=8 days

Practice this question

Try it yourself before checking the explanation above.

A and B can complete a task in 40 days and 16 days respectively. A started the task alone and then after 12 days B joined him till the completion of the task. How long did the task last after B joined the task?
A
8 days
B
6 days
C
14 days
D
12 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion