A and B can do a piece of work in 10 days. B and C can do the same work in 12 days. C and A can do the same work in 15 days. If all the three work together, find the number of days required to complete the work.
- A12
- B6
- C10
- D8
Solution & Step-by-step Explanation
Let the total work be the LCM of 10, 12, and 15, which is 60 units.
Calculating individual combined efficiencies per day:
Efficiency of (A+B)=
10
60
=6 units/day
Efficiency of (B+C)=
12
60
=5 units/day
Efficiency of (C+A)=
15
60
=4 units/day
Adding all three equations:
2(A+B+C)=6+5+4=15 units/day
Efficiency of (A+B+C)=
2
15
=7.5 units/day
Number of days required by A, B, and C working together:
Days=
Total Efficiency
Total Work
=
7.5
60
=
15
60×2
=8 days
Calculating individual combined efficiencies per day:
Efficiency of (A+B)=
10
60
=6 units/day
Efficiency of (B+C)=
12
60
=5 units/day
Efficiency of (C+A)=
15
60
=4 units/day
Adding all three equations:
2(A+B+C)=6+5+4=15 units/day
Efficiency of (A+B+C)=
2
15
=7.5 units/day
Number of days required by A, B, and C working together:
Days=
Total Efficiency
Total Work
=
7.5
60
=
15
60×2
=8 days