HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
1 mark

A and B can do a piece of work separately in 10 days and 8 days, respectively. If they work alternately and A begins the work, in how many days will the work be completed?

  1. A
    10
  2. B
    8
  3. C
    9
  4. D
    12

Solution & Step-by-step Explanation

Let's find the total work by taking the LCM of the time taken by A and B.
Total Work=LCM(10,8)=40 units
Now, determine their individual daily efficiencies:

Efficiency of A=
10
40

=4 units/day

Efficiency of B=
8
40

=5 units/day

They work on alternate days starting with A:

Day 1 (A): 4 units

Day 2 (B): 5 units

In a 2-day cycle, the total work completed is:

4+5=9 units
To get close to 40 units, multiply by 4 full cycles:

Work done in 4×2=8 days=4×9=36 units
Remaining work after 8 days:

40−36=4 units
On the 9
th
day, it is A's turn to work. A can do 4 units of work in a full day.
Since the remaining work is exactly 4 units, A will complete it in exactly 1 day.

Total time taken = 8+1=9 days.

Practice this question

Try it yourself before checking the explanation above.

A and B can do a piece of work separately in 10 days and 8 days, respectively. If they work alternately and A begins the work, in how many days will the work be completed?
A
10
B
8
C
9
D
12

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion