and can do a work in days and days, respectively. If they work for a day alternately, starting with , then in how many days will the work be completed?
- A
- B
- C
- D
Solution & Step-by-step Explanation
Time taken by days
Time taken by days
Let the total work be the Least Common Multiple (LCM) of and :
Now, determine the individual efficiencies:
They work alternately starting with :
* Day 1 ():
* Day 2 ():
Work completed in cycle of days:
Number of complete -day cycles required to get close to units:
Work done in complete cycles ( days):
Remaining work:
On the day, it is 's turn. Time taken by to finish the remaining units:
Total days taken to complete the entire work:
Time taken by days
Let the total work be the Least Common Multiple (LCM) of and :
Now, determine the individual efficiencies:
They work alternately starting with :
* Day 1 ():
* Day 2 ():
Work completed in cycle of days:
Number of complete -day cycles required to get close to units:
Work done in complete cycles ( days):
Remaining work:
On the day, it is 's turn. Time taken by to finish the remaining units:
Total days taken to complete the entire work: