HomeTestsSearchRankProfile
mediumMCQSSC CGL2026Quantitative Aptitude
4 attempts25% success rate1 mark

A and B can separately finish a work in 15 and 20 days, respectively. A starts the work and B joins him from the fifth day. How much time will it take to finish the complete work?

  1. A
    10
    7
    2

    days
  2. B
    11
    7
    3

    days
  3. C
    11 days
  4. D
    10 days

Solution & Step-by-step Explanation

Let the total work be the Least Common Multiple (LCM) of 15 and 20.
Total Work=LCM(15,20)=60 units
Now, find the daily efficiency of A and B:

Efficiency of A=
15
60

=4 units/day
Efficiency of B=
20
60

=3 units/day
A starts the work alone and works for the first 4 days (since B joins from the fifth day):

Work done by A in 4 days=4×4=16 units
Remaining work to be completed:

Remaining Work=60−16=44 units
From the fifth day onwards, both A and B work together:

Combined Efficiency of A+B=4+3=7 units/day
Time taken by both to finish the remaining work=
7
44

=6
7
2

 days
Total time taken to finish the complete work:

Total Time=4 days+6
7
2

 days=10
7
2

 days

Practice this question

Try it yourself before checking the explanation above.

A and B can separately finish a work in 15 and 20 days, respectively. A starts the work and B joins him from the fifth day. How much time will it take to finish the complete work?
A
10
7
2

days
B
11
7
3

days
C
11 days
D
10 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion