HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
1 mark

A and B complete a work in 12 and 15 days, respectively. They started the work alternatively for 1 day each and A started the work first. In how much time will 60% of the work be completed?

  1. A
    9 days
  2. B
    10 days
  3. C
    7 days
  4. D
    8 days

Solution & Step-by-step Explanation

Let the total work be the LCM of 12 and 15, which is 60 units.
Efficiency of A =
12
60

=5 units/day

Efficiency of B =
15
60

=4 units/day

We need to find the time taken to complete 60% of the work:

Target work=60% of 60=0.60×60=36 units
They work on alternate days starting with A:

Day 1 (A): 5 units

Day 2 (B): 4 units

In a 2-day cycle, the total work done is:

5+4=9 units
To complete 36 units:

Number of cycles=
9
36

=4 cycles
Since each cycle consists of 2 days:

Total time=4×2=8 days

Practice this question

Try it yourself before checking the explanation above.

A and B complete a work in 12 and 15 days, respectively. They started the work alternatively for 1 day each and A started the work first. In how much time will 60% of the work be completed?
A
9 days
B
10 days
C
7 days
D
8 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion