mediumMCQCompetitive Exam2026Quantitative Aptitude@NUM: 56
1 mark

A, B and C can complete a certain work in , and days, respectively. A and B together start the work and B leaves after working for days. A and C together will complete the remaining work in ______ days.

  1. A
    three
  2. B
    six
  3. C
    five
  4. D
    four

Solution & Step-by-step Explanation

Let's find the total work by taking the Least Common Multiple (LCM) of the days taken by A, B, and C.

Now, let's find the daily efficiency of each individual:Efficiency of A = Efficiency of B = Efficiency of C = Step 1: Work done by A and B together for 4 daysCombined efficiency of A and B = Work done in 4 days = Step 2: Calculate remaining workRemaining work = Step 3: Time taken by A and C to finish remaining workCombined efficiency of A and C = Time taken by A and C =

Practice this question

Try it yourself before checking the explanation above.

A, B and C can complete a certain work in , and days, respectively. A and B together start the work and B leaves after working for days. A and C together will complete the remaining work in ______ days.
A
three
B
six
C
five
D
four