HomeTestsSearchRankProfile
mediumMCQSSC CGL2026Quantitative Aptitude
1 mark

A, B and C can do a piece of work in 20 days, 30 days and 60 days, respectively, working alone. How soon can the work be done if A is assisted by B and C each on every alternate day?

  1. A
    3
    40

     days
  2. B
    3
    28

     days
  3. C
    4
    37

     days
  4. D
    4
    53

     days

Solution & Step-by-step Explanation

Let the total work be the LCM of 20,30, and 60, which is 60 units.
Efficiencies of A, B, and C:

Efficiency of A =
20
60

=3 units/day

Efficiency of B =
30
60

=2 units/day

Efficiency of C =
60
60

=1 units/day

According to the alternate day cycle pattern:

Day 1: A is assisted by B ⟹Work done=A+B=3+2=5 units

Day 2: A is assisted by C ⟹Work done=A+C=3+1=4 units

In a 2-day cycle, the amount of work completed is:

Work in 2 days=5+4=9 units
To get close to the total work of 60 units, let's multiply by 6 cycles:

Work in 6×2=12 days⟹6×9=54 units
Remaining work = 60−54=6 units.

On Day 13, it is the turn of (A + B), who can complete 5 units of work.

Remaining work after Day 13=6−5=1 unit
Total time passed=13 days
On Day 14, it is the turn of (A + C), who can do 4 units of work per day.
Time required to finish the final 1 unit =
4
1

 days.

Total time taken = 13+
4
1

=
4
53

 days.

Practice this question

Try it yourself before checking the explanation above.

A, B and C can do a piece of work in 20 days, 30 days and 60 days, respectively, working alone. How soon can the work be done if A is assisted by B and C each on every alternate day?
A
3
40

 days
B
3
28

 days
C
4
37

 days
D
4
53

 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion