HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
4 attempts0% success rate1 mark

A, B and C can do the same work in 9 days, 12 days and 18 days, respectively. A started the work and worked for 3 days and left. Then, B joined the work and worked for 3 days and left. Then, C joined the work and completed the work. Find the number of days C took to complete the work.

  1. A
  2. B
    7
  3. C
    8
  4. D

Solution & Step-by-step Explanation

Let the total work be the LCM of 9, 12, and 18, which is 36 units.Efficiency of A = units/dayEfficiency of B = units/dayEfficiency of C = units/dayWork done by A in 3 days = units.Work done by B in 3 days = units.Total work completed by A and B = units.Remaining work = units.Number of days taken by C to complete the remaining work = $
$

Practice this question

Try it yourself before checking the explanation above.

A, B and C can do the same work in 9 days, 12 days and 18 days, respectively. A started the work and worked for 3 days and left. Then, B joined the work and worked for 3 days and left. Then, C joined the work and completed the work. Find the number of days C took to complete the work.
A
B
7
C
8
D

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion