A, B and C can do the same work in 9 days, 12 days and 18 days, respectively. A started the work and worked for 3 days and left. Then, B joined the work and worked for 3 days and left. Then, C joined the work and completed the work. Find the number of days C took to complete the work.
- A
- B7
- C8
- D
Solution & Step-by-step Explanation
Let the total work be the LCM of 9, 12, and 18, which is 36 units.Efficiency of A = units/dayEfficiency of B = units/dayEfficiency of C = units/dayWork done by A in 3 days = units.Work done by B in 3 days = units.Total work completed by A and B = units.Remaining work = units.Number of days taken by C to complete the remaining work = $
$
$