HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
1 mark

A can complete 25% of the work in 4 days, B can complete 50% of the same work in 12 days and C can complete the same work in 32 days. They started working together but C left after 4 days of the start and A left 6 days before the completion of the work. In how many days was the work completed?

  1. A
    10 days
  2. B
    12 days
  3. C
    8 days
  4. D
    14 days

Solution & Step-by-step Explanation

Find the total number of days required by each individual to complete the entire work:
A completes 25% (
4
1

) of the work in 4 days → Total time for A =4×4=16 days.

B completes 50% (
2
1

) of the work in 12 days → Total time for B =12×2=24 days.

C completes the full work in 32 days → Total time for C =32 days.

Let the total work be the LCM of 16,24,32, which is 96 units.

Efficiencies (work done per day):

Efficiency of A =
16
96

=6 units/day

Efficiency of B =
24
96

=4 units/day

Efficiency of C =
32
96

=3 units/day

Let the total work be completed in x days.

C worked for 4 days.

A left 6 days before completion, so A worked for (x−6) days.

B worked for the entire duration of x days.

Formulating the work equation:

Work done by A+Work done by B+Work done by C=Total Work
6(x−6)+4x+3(4)=96
6x−36+4x+12=96
10x−24=96
10x=120
x=12 days

Practice this question

Try it yourself before checking the explanation above.

A can complete 25% of the work in 4 days, B can complete 50% of the same work in 12 days and C can complete the same work in 32 days. They started working together but C left after 4 days of the start and A left 6 days before the completion of the work. In how many days was the work completed?
A
10 days
B
12 days
C
8 days
D
14 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion