HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
1 mark

A can complete 40% of a work in 6 days and B can complete 33
3
1

% of the same work in 8 days. They work together for 8 days. C alone completes the remaining work in 4 days. A and C together will complete the same work in:

  1. A
    13
    8
    1

    days
  2. B
    12 days
  3. C
    9 days
  4. D
    10 days

Solution & Step-by-step Explanation

Total days needed by A and B to finish the work:
A completes 40% (
5
2

) of the work in 6 days → Total days for A =6×
2
5

=15 days.

B completes 33
3
1

% (
3
1

) of the work in 8 days → Total days for B =8×3=24 days.

Let the total work be the LCM of 15 and 24, which is 120 units.

Efficiencies:

Efficiency of A =
15
120

=8 units/day

Efficiency of B =
24
120

=5 units/day

Combined efficiency of A and B =8+5=13 units/day.

Work completed by A and B in 8 days:

Work done=13×8=104 units
Remaining work:

Remaining work=120−104=16 units
C completes this remaining work in 4 days:

Efficiency of C=
4
16

=4 units/day
Combined efficiency of A and C =8+4=12 units/day.

Time taken by A and C together to complete the entire work:

Time=
12
120

=10 days

Practice this question

Try it yourself before checking the explanation above.

A can complete 40% of a work in 6 days and B can complete 33
3
1

% of the same work in 8 days. They work together for 8 days. C alone completes the remaining work in 4 days. A and C together will complete the same work in:
A
13
8
1

days
B
12 days
C
9 days
D
10 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion