A can complete 40% of a work in 6 days and B can complete 33
3
1
% of the same work in 8 days. They work together for 8 days. C alone completes the remaining work in 4 days. A and C together will complete the same work in:
- A13
8
1
days - B12 days
- C9 days
- D10 days
Solution & Step-by-step Explanation
Total days needed by A and B to finish the work:
A completes 40% (
5
2
) of the work in 6 days → Total days for A =6×
2
5
=15 days.
B completes 33
3
1
% (
3
1
) of the work in 8 days → Total days for B =8×3=24 days.
Let the total work be the LCM of 15 and 24, which is 120 units.
Efficiencies:
Efficiency of A =
15
120
=8 units/day
Efficiency of B =
24
120
=5 units/day
Combined efficiency of A and B =8+5=13 units/day.
Work completed by A and B in 8 days:
Work done=13×8=104 units
Remaining work:
Remaining work=120−104=16 units
C completes this remaining work in 4 days:
Efficiency of C=
4
16
=4 units/day
Combined efficiency of A and C =8+4=12 units/day.
Time taken by A and C together to complete the entire work:
Time=
12
120
=10 days
A completes 40% (
5
2
) of the work in 6 days → Total days for A =6×
2
5
=15 days.
B completes 33
3
1
% (
3
1
) of the work in 8 days → Total days for B =8×3=24 days.
Let the total work be the LCM of 15 and 24, which is 120 units.
Efficiencies:
Efficiency of A =
15
120
=8 units/day
Efficiency of B =
24
120
=5 units/day
Combined efficiency of A and B =8+5=13 units/day.
Work completed by A and B in 8 days:
Work done=13×8=104 units
Remaining work:
Remaining work=120−104=16 units
C completes this remaining work in 4 days:
Efficiency of C=
4
16
=4 units/day
Combined efficiency of A and C =8+4=12 units/day.
Time taken by A and C together to complete the entire work:
Time=
12
120
=10 days