A can complete a piece of work in 12 days while B can do the same work in 18 days. If they both work together, then how many days will be required to finish the work?

  1. A
    6.5
  2. B
    6
  3. C
    7
  4. D
    7.2

Solution & Step-by-step Explanation

Let the total work be the LCM of 12 and 18.
Total Work=LCM(12,18)=36units
Calculate the efficiencies (work done per day):

Efficiency of A=
12
36

=3units/day

Efficiency of B=
18
36

=2units/day

Combined efficiency of A and B:

Total Efficiency=3+2=5units/day
Time required to finish the work together:

Time=
Total Efficiency
Total Work

=
5
36

=7.2days

Practice this question

Try it yourself before checking the explanation above.

A can complete a piece of work in 12 days while B can do the same work in 18 days. If they both work together, then how many days will be required to finish the work?
A
6.5
B
6
C
7
D
7.2

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion