A can do a certain work in 40 days. B is 60% more efficient than A. Both work together for 10 days. C alone completes the remaining work in 10
2
1
days. Working together, B and C can complete 44% of the original work in:
- A8 days
- B6 days
- C5 days
- D9 days
Solution & Step-by-step Explanation
Let the efficiency of A be 5 units/day.
Since B is 60% more efficient than A, efficiency of B =5×1.6=8 units/day.
Total Work =Efficiency of A×Days=5×40=200 units.
A and B work together for 10 days:
Work done by A and B=(5+8)×10=13×10=130 units
Remaining Work=200−130=70 units
C completes the remaining work in 10
2
1
=
2
21
days:
Efficiency of C=
2
21
70
=
21
140
=
3
20
units/day
Combined efficiency of B and C:
Efficiency of B + C=8+
3
20
=
3
44
units/day
We need to find the time taken to complete 44% of the original work:
Targeted Work=44% of 200=
100
44
×200=88 units
Time taken by B and C:
Time=
3
44
88
=
44
88×3
=2×3=6 days
Since B is 60% more efficient than A, efficiency of B =5×1.6=8 units/day.
Total Work =Efficiency of A×Days=5×40=200 units.
A and B work together for 10 days:
Work done by A and B=(5+8)×10=13×10=130 units
Remaining Work=200−130=70 units
C completes the remaining work in 10
2
1
=
2
21
days:
Efficiency of C=
2
21
70
=
21
140
=
3
20
units/day
Combined efficiency of B and C:
Efficiency of B + C=8+
3
20
=
3
44
units/day
We need to find the time taken to complete 44% of the original work:
Targeted Work=44% of 200=
100
44
×200=88 units
Time taken by B and C:
Time=
3
44
88
=
44
88×3
=2×3=6 days