HomeTestsSearchRankProfile
mediumMCQSSC CGL2026Quantitative Aptitude
1 mark

A can do a certain work in 40 days. B is 60% more efficient than A. Both work together for 10 days. C alone completes the remaining work in 10
2
1

days. Working together, B and C can complete 44% of the original work in:

  1. A
    8 days
  2. B
    6 days
  3. C
    5 days
  4. D
    9 days

Solution & Step-by-step Explanation

Let the efficiency of A be 5 units/day.
Since B is 60% more efficient than A, efficiency of B =5×1.6=8 units/day.

Total Work =Efficiency of A×Days=5×40=200 units.

A and B work together for 10 days:

Work done by A and B=(5+8)×10=13×10=130 units
Remaining Work=200−130=70 units
C completes the remaining work in 10
2
1

=
2
21

days:

Efficiency of C=
2
21


70

=
21
140

=
3
20

 units/day
Combined efficiency of B and C:

Efficiency of B + C=8+
3
20

=
3
44

 units/day
We need to find the time taken to complete 44% of the original work:

Targeted Work=44% of 200=
100
44

×200=88 units
Time taken by B and C:

Time=
3
44


88

=
44
88×3

=2×3=6 days

Practice this question

Try it yourself before checking the explanation above.

A can do a certain work in 40 days. B is 60% more efficient than A. Both work together for 10 days. C alone completes the remaining work in 10
2
1

days. Working together, B and C can complete 44% of the original work in:
A
8 days
B
6 days
C
5 days
D
9 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion