HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
1 attempts0% success rate1 mark

A can do a piece of work in 63 days and B is more efficient than A. Then the number of days taken by B to do the same work is:

  1. A
    60 days
  2. B
    45 days
  3. C
    49 days
  4. D
    40 days

Solution & Step-by-step Explanation

Let the efficiency of A be 100.
Since B is more efficient than A, efficiency of B = .

The ratio of efficiency of A to B is:



Since efficiency is inversely proportional to the time taken to complete the work:



Given that A takes 63 days:





Therefore, the number of days taken by B:

Practice this question

Try it yourself before checking the explanation above.

A can do a piece of work in 63 days and B is more efficient than A. Then the number of days taken by B to do the same work is:
A
60 days
B
45 days
C
49 days
D
40 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion