A can do a work in 12 days and B in 18 days. If they work on it together for 4 days, then what fraction of work is left?

  1. A
    4/9
  2. B
    5/9
  3. C
    5/36
  4. D
    7/36

Solution & Step-by-step Explanation

Let the total work be the LCM of 12 and 18, which is 36 units.
Efficiency of A =
12
36

=3 units/day

Efficiency of B =
18
36

=2 units/day

Combined efficiency of A and B = 3+2=5 units/day

Work done by both working together in 4 days:

Work done=5×4=20 units
Remaining work:

Remaining work=36−20=16 units
Fraction of work left:

Fraction left=
36
16

=
9
4

Practice this question

Try it yourself before checking the explanation above.

A can do a work in 12 days and B in 18 days. If they work on it together for 4 days, then what fraction of work is left?
A
4/9
B
5/9
C
5/36
D
7/36