HomeTestsSearchRankProfile
mediumMCQStaff Selection Commission2026Quantitative Aptitude
1 attempts0% success rate1 mark

A can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed?

  1. A
    17.5
  2. B
    10
  3. C
    15
  4. D
    12

Solution & Step-by-step Explanation

Step 1: Find total time required by A and B individually to complete 100% of the task.
A completes 80% (
5
4

) of the task in 12 days.

Total time taken by A=12×
4
5

=15 days
B completes 20% (
5
1

) of the task in 2 days.

Total time taken by B=2×5=10 days
Step 2: Define total work and efficiencies.
Let Total Work = LCM(15,10)=30 units.

Efficiency of A =
15
30

=2 units/day

Efficiency of B =
10
30

=3 units/day

Step 3: Calculate work done together in 2 days.
Work done by A and B together in 1 day = 2+3=5 units
Work done in 2 days = 5×2=10 units

Step 4: Calculate remaining work and time taken by A to finish it.
Remaining work = 30−10=20 units
Time taken by A to finish the remaining work =
2
20

=10 days

Step 5: Find total time for the entire task.

Total time=Initial 2 days with B+10 days by A alone=12 days

Practice this question

Try it yourself before checking the explanation above.

A can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed?
A
17.5
B
10
C
15
D
12

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion