HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
1 attempts0% success rate1 mark

A can finish as much work in 6 days as C can in 8 days. B can finish as much work in 6 days as C can in 4 days. How much time will B require to finish a work if A takes 54 days to finish it?

  1. A
    118 days
  2. B
    128 days
  3. C
    100 days
  4. D
    108 days

Solution & Step-by-step Explanation

Let the work efficiencies (work done per day) of A,B, and C be denoted by E
A

,E
B

, and E
C

respectively.

From the first statement:

Work done by A in 6 days=Work done by C in 8 days
6×E
A

=8×E
C


E
C


E
A



=
6
8

=
3
4


From the second statement:

Work done by B in 6 days=Work done by C in 4 days
6×E
B

=4×E
C


E
C


E
B



=
6
4

=
3
2


From these ratios, we can express the efficiencies of A and B relative to C:

E
A

=4k,E
B

=2k,E
C

=3k
Given that A takes 54 days to finish the work:

Total Work=Efficiency of A×Time taken by A
Total Work=4k×54=216k
Now, we calculate the time required by B to finish the same work:

Time taken by B=
Efficiency of B
Total Work

=
2k
216k

=108 days

Practice this question

Try it yourself before checking the explanation above.

A can finish as much work in 6 days as C can in 8 days. B can finish as much work in 6 days as C can in 4 days. How much time will B require to finish a work if A takes 54 days to finish it?
A
118 days
B
128 days
C
100 days
D
108 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion