HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
1 mark

A can finish one-third of a work in 5 days, and B can finish 50% of the same work in 15 days. If they work together, then in how many days will they finish 50% of the work?

  1. A
    10
  2. B
    4
  3. C
    8
  4. D
    5

Solution & Step-by-step Explanation

Time taken by A to complete
3
1

of the work = 5 days.

Total time taken by A to complete the entire work (T
A

)=5×3=15 days.
Time taken by B to complete 50% (
2
1

) of the work = 15 days.

Total time taken by B to complete the entire work (T
B

)=15×2=30 days.
Let the total work be the LCM of 15 and 30, which is 30 units.

Efficiency of A=
15
30

=2 units/day
Efficiency of B=
30
30

=1 unit/day
Combined efficiency of A and B=2+1=3 units/day
We need to find the time taken to finish 50% of the work.

Work to be done=50% of 30=15 units
Time taken=
Combined efficiency
Work

=
3
15

=5 days.

Practice this question

Try it yourself before checking the explanation above.

A can finish one-third of a work in 5 days, and B can finish 50% of the same work in 15 days. If they work together, then in how many days will they finish 50% of the work?
A
10
B
4
C
8
D
5

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion