A ceramic pottery unit hires 8 craftsmen by paying each of them Rs 900 per day. The 9th craftsman demands Rs 950 per day. If this craftsman is hired then all other craftsmen must be paid Rs 950. The marginal resource (labour) cost of the 9th craftsman is ________.
- ARs 1530
- BRs 1050
- CRs 50
- DRs 1350
Solution & Step-by-step Explanation
Initial Total Cost for craftsmen:
New Total Cost for craftsmen (since all are now paid ):
The Marginal Resource (Labour) Cost () of hiring the craftsman is:
New Total Cost for craftsmen (since all are now paid ):
The Marginal Resource (Labour) Cost () of hiring the craftsman is: