A completes a piece of work in 4 days and B completes it in 6 days. How long will it take to complete the same piece of work if they both work together?

  1. A
    2
    5
    2

     days
  2. B
    3 days
  3. C
    2
    2
    1

     days
  4. D
    4 days

Solution & Step-by-step Explanation

Time taken by A=4 days
Time taken by B=6 days

Let the total work be the LCM of 4 and 6, which is 12 units.

Efficiency of A=
4
12

=3 units/day
Efficiency of B=
6
12

=2 units/day

Combined efficiency of A and B=3+2=5 units/day

Time taken by both working together =
Combined Efficiency
Total Work

=
5
12

=2
5
2

 days.

Practice this question

Try it yourself before checking the explanation above.

A completes a piece of work in 4 days and B completes it in 6 days. How long will it take to complete the same piece of work if they both work together?
A
2
5
2

 days
B
3 days
C
2
2
1

 days
D
4 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion