A contractor undertakes to make a tunnel in days and employs men. After days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work days earlier?
- A60 men
- B70 men
- C100 men
- D75 men
Solution & Step-by-step Explanation
Let's use the work equivalence formula:
Given parameters for the first part of the work:
*
*
*
Parameters for the remaining part of the work:
* Remaining work:
* Total time scheduled initially was days. Since the contractor wants to finish the work days earlier, the total target time becomes days.
* Time already spent: days.
* Remaining days available: days.
* Let total men working in the second phase be .
Substituting these values into the formula:
Canceling out the denominators:
Therefore, the total number of men required is .
The number of extra men to employ is:
Given parameters for the first part of the work:
*
*
*
Parameters for the remaining part of the work:
* Remaining work:
* Total time scheduled initially was days. Since the contractor wants to finish the work days earlier, the total target time becomes days.
* Time already spent: days.
* Remaining days available: days.
* Let total men working in the second phase be .
Substituting these values into the formula:
Canceling out the denominators:
Therefore, the total number of men required is .
The number of extra men to employ is: