A does 50% of a work in 12 days. He then calls in B and they together finish the remaining work in 8 days. How long B alone would take to complete the whole work?
- A12 days
- B24 days
- C36 days
- D48 days
Solution & Step-by-step Explanation
A completes 50% (or
2
1
) of the work in 12 days.
Therefore, A can complete the whole work alone in:
12×2=24 days
So, A's 1-day work rate =
24
1
The remaining work is 100%−50%=50% (or
2
1
).
A and B together finish this remaining
2
1
work in 8 days.
Therefore, A and B together can complete the whole work in:
8×2=16 days
So, (A + B)'s 1-day work rate =
16
1
Now, B's 1-day work rate can be found by subtracting A's rate from their combined rate:
B’s 1-day work=
16
1
−
24
1
Taking the LCM of 16 and 24, which is 48:
B’s 1-day work=
48
3−2
=
48
1
Thus, B alone would take 48 days to complete the whole work.
2
1
) of the work in 12 days.
Therefore, A can complete the whole work alone in:
12×2=24 days
So, A's 1-day work rate =
24
1
The remaining work is 100%−50%=50% (or
2
1
).
A and B together finish this remaining
2
1
work in 8 days.
Therefore, A and B together can complete the whole work in:
8×2=16 days
So, (A + B)'s 1-day work rate =
16
1
Now, B's 1-day work rate can be found by subtracting A's rate from their combined rate:
B’s 1-day work=
16
1
−
24
1
Taking the LCM of 16 and 24, which is 48:
B’s 1-day work=
48
3−2
=
48
1
Thus, B alone would take 48 days to complete the whole work.