HomeTestsSearchRankProfile
mediumMCQSSC CGL2026Quantitative Aptitude
1 attempts0% success rate1 mark

A does 50% of a work in 12 days. He then calls in B and they together finish the remaining work in 8 days. How long B alone would take to complete the whole work?

  1. A
    12 days
  2. B
    24 days
  3. C
    36 days
  4. D
    48 days

Solution & Step-by-step Explanation

A completes 50% (or
2
1

) of the work in 12 days.
Therefore, A can complete the whole work alone in:

12×2=24 days
So, A's 1-day work rate =
24
1



The remaining work is 100%−50%=50% (or
2
1

).
A and B together finish this remaining
2
1

work in 8 days.
Therefore, A and B together can complete the whole work in:

8×2=16 days
So, (A + B)'s 1-day work rate =
16
1



Now, B's 1-day work rate can be found by subtracting A's rate from their combined rate:

B’s 1-day work=
16
1


24
1


Taking the LCM of 16 and 24, which is 48:

B’s 1-day work=
48
3−2

=
48
1


Thus, B alone would take 48 days to complete the whole work.

Practice this question

Try it yourself before checking the explanation above.

A does 50% of a work in 12 days. He then calls in B and they together finish the remaining work in 8 days. How long B alone would take to complete the whole work?
A
12 days
B
24 days
C
36 days
D
48 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion