HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
1 mark

A does 75% of a work in 45 days. He then calls in B and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?

  1. A
    15 days
  2. B
    45 days
  3. C
    60 days
  4. D
    30 days

Solution & Step-by-step Explanation

A completes 75% (
4
3

) of the work in 45 days.
Time taken by A to complete the whole work alone = 45×
3
4

=60 days.
So, A's 1-day work rate =
60
1

.

Remaining work = 100%−75%=25% (
4
1

).
A and B together complete this remaining
4
1

work in 5 days.
Time taken by A and B together to do the whole work = 5×4=20 days.
So, (A + B)'s 1-day work rate =
20
1

.

B's 1-day work rate = (A + B)'s 1-day rate - A's 1-day rate

B’s 1-day rate=
20
1


60
1

=
60
3−1

=
60
2

=
30
1


Therefore, B alone can complete the work in 30 days.

Practice this question

Try it yourself before checking the explanation above.

A does 75% of a work in 45 days. He then calls in B and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?
A
15 days
B
45 days
C
60 days
D
30 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion