HomeTestsSearchRankProfile
mediumMCQSSC Competitive Exams2026Quantitative Aptitude
1 mark

A group of men decided to complete a job in 4 days. However, since 10 men dropped out every day, the job got completed at the end of the 7th day. How many men were there in the beginning?

  1. A
    140
  2. B
    70
  3. C
    35
  4. D
    90

Solution & Step-by-step Explanation

Let the initial number of men be x.
Let the efficiency of one man be 1 unit of work per day.

Total work to be done = 4×x=4x units.

According to the given condition, 10 men drop out every day, and the work finishes in 7 days.
The number of men working on consecutive days is:

Day 1: x

Day 2: x−10

Day 3: x−20

Day 4: x−30

Day 5: x−40

Day 6: x−50

Day 7: x−60

Total work done in these 7 days:

Total Work=x+(x−10)+(x−20)+(x−30)+(x−40)+(x−50)+(x−60)
4x=7x−(10+20+30+40+50+60)
4x=7x−210
3x=210
x=70
Thus, there were 70 men in the beginning.

Practice this question

Try it yourself before checking the explanation above.

A group of men decided to complete a job in 4 days. However, since 10 men dropped out every day, the job got completed at the end of the 7th day. How many men were there in the beginning?
A
140
B
70
C
35
D
90

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion