A machine can complete double the work that a man can complete in a given period of time. To complete a work, 10 machines and 5 men take 60 days. If there were 10 men and 5 machines, then the time it would have taken to complete the work is:

  1. A
    90 days
  2. B
    84 days
  3. C
    68 days
  4. D
    75 days

Solution & Step-by-step Explanation

Let the efficiency of a man be M and the efficiency of a machine be M
c

.
Given that a machine does double the work of a man in the same time:

M
c

=2M
Case 1: 10 machines and 5 men take 60 days.

Total efficiency=10M
c

+5M=10(2M)+5M=20M+5M=25M
Total Work=Total efficiency×Days=25M×60=1500M
Case 2: Find the time taken (D) by 10 men and 5 machines to complete the same work.

New efficiency=10M+5M
c

=10M+5(2M)=10M+10M=20M
Time taken (D)=
New efficiency
Total Work

=
20M
1500M

=75 days

Practice this question

Try it yourself before checking the explanation above.

A machine can complete double the work that a man can complete in a given period of time. To complete a work, 10 machines and 5 men take 60 days. If there were 10 men and 5 machines, then the time it would have taken to complete the work is:
A
90 days
B
84 days
C
68 days
D
75 days