Abhay can do a work in 22 days. Nidhi is 28% more efficient than Abhay. The number of days Nidhi will take to do the same piece of work is:

  1. A
    17
    16
    3

    days
  2. B
    16
    17
    3

    days
  3. C
    17
    16
    1

    days
  4. D
    16
    17
    1

    days

Solution & Step-by-step Explanation

Let the efficiency of Abhay be 100.
Since Nidhi is 28% more efficient than Abhay, the efficiency of Nidhi is:

100+28=128
The ratio of efficiency of Abhay to Nidhi is:

E
A

:E
N

=100:128=25:32
We know that efficiency is inversely proportional to the time taken:

T
A


T
N



=
E
N


E
A




22
T
N



=
32
25


T
N

=
32
25×22

=
16
25×11

=
16
275


Converting
16
275

into a mixed fraction:

275=16×17+3
T
N

=17
16
3

 days

Practice this question

Try it yourself before checking the explanation above.

Abhay can do a work in 22 days. Nidhi is 28% more efficient than Abhay. The number of days Nidhi will take to do the same piece of work is:
A
17
16
3

days
B
16
17
3

days
C
17
16
1

days
D
16
17
1

days