At a construction site, 15 men or 10 machines can construct a room in 66 days. In how many days can 5 men and 4 machines together complete the work?

  1. A
    80
  2. B
    75
  3. C
    85
  4. D
    90

Solution & Step-by-step Explanation

Given that the work done by 15 men is equal to the work done by 10 machines:
15 Men=10 Machines
1 Men=
15
10

 Machines=
3
2

 Machines
Total work in terms of machines can be given as:

Total Work=10 machines×66 days=660 machine-days
Now, we need to find the work done by 5 men and 4 machines together. Convert men into machines:

5 men+4 machines=5×(
3
2

) machines+4 machines
=
3
10

+4=
3
22

 machines
Let D be the number of days required by them to finish the work:

3
22

×D=660
D=
22
660×3


D=30×3=90 days

Practice this question

Try it yourself before checking the explanation above.

At a construction site, 15 men or 10 machines can construct a room in 66 days. In how many days can 5 men and 4 machines together complete the work?
A
80
B
75
C
85
D
90