Eight men can complete a work in 54 days. In how many days will 6 men and 12 boys complete the same work if one man works as much as 2 boys?

  1. A
    36
  2. B
    30
  3. C
    24
  4. D
    40

Solution & Step-by-step Explanation

Given the efficiency relationship:
1 Man=2 Boys⟹Efficiency ratio (M : B)=2:1
Let:

Efficiency of a man = 2 units/day

Efficiency of a boy = 1 unit/day

First, calculate the total work:

Total Work=8 Men×54 days=8×2×54=864 units
Now, find the combined efficiency of 6 men and 12 boys:

Combined Efficiency=(6×2)+(12×1)=12+12=24 units/day
The time required to complete the same work is:

Time=
Combined Efficiency
Total Work

=
24
864

=36 days

Practice this question

Try it yourself before checking the explanation above.

Eight men can complete a work in 54 days. In how many days will 6 men and 12 boys complete the same work if one man works as much as 2 boys?
A
36
B
30
C
24
D
40

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion