How many workers would be needed to complete the same task in days if it takes days for workers to complete a task?
- A28
- B25
- C18
- D22
Solution & Step-by-step Explanation
Using the work-equivalence formula :
* Initial workers ()
* Initial days ()
* Target days ()
* Initial workers ()
* Initial days ()
* Target days ()