If 28 men can do a piece of work in 26 days, then in how many days 13 men will do it?

  1. A
    52
  2. B
    56
  3. C
    50
  4. D
    58

Solution & Step-by-step Explanation

We can use the formula connecting man-power and time taken:
M
1

×D
1

=M
2

×D
2


Given data:

M
1

=28 men

D
1

=26 days

M
2

=13 men

D
2

=?

Substituting the values into the formula:

28×26=13×D
2


D
2

=
13
28×26


D
2

=28×2=56 days