If 72 boys can build a wall of length in 21 days, how many boys would take 18 days to build a similar type of wall of length ?

  1. A
    60 boys
  2. B
    40 boys
  3. C
    48 boys
  4. D
    28 boys

Solution & Step-by-step Explanation

We can use the chain rule formula:


Where:

* boys
* days
*
* days
*
* number of boys required

Substituting the values into the equation:



Solving for :













So, 60 boys are required.