If 72 boys can build a wall of length in 21 days, how many boys would take 18 days to build a similar type of wall of length ?
- A60 boys
- B40 boys
- C48 boys
- D28 boys
Solution & Step-by-step Explanation
We can use the chain rule formula:
Where:
* boys
* days
*
* days
*
* number of boys required
Substituting the values into the equation:
Solving for :
So, 60 boys are required.
Where:
* boys
* days
*
* days
*
* number of boys required
Substituting the values into the equation:
Solving for :
So, 60 boys are required.