P alone can do a piece of work in 8 days and Q alone can do the same work in 10 days. In how many days will both together complete the same work?

  1. A
    40/9
  2. B
    20/9
  3. C
    60/7
  4. D
    40/7

Solution & Step-by-step Explanation

Work done by P in 1 day =
8
1


Work done by Q in 1 day =
10
1



Work done by both P and Q together in 1 day:

8
1

+
10
1

=
40
5+4

=
40
9


Therefore, the number of days required for both to complete the work together is:

Days=
9
40

Practice this question

Try it yourself before checking the explanation above.

P alone can do a piece of work in 8 days and Q alone can do the same work in 10 days. In how many days will both together complete the same work?
A
40/9
B
20/9
C
60/7
D
40/7