and can do a project in and days respectively. In how many days can they complete of the project if they work together?
- A
- B
- C
- D
Solution & Step-by-step Explanation
Let the total work be the LCM of and , which is .Efficiency of Efficiency of Combined efficiency of and We need to find the time taken to complete of the project: