P and Q can do a project in 25 and 50 days respectively. In how many days can they complete 18% of the project if they work together?

  1. A
    6 days
  2. B
    3 days
  3. C
    12 days
  4. D
    9 days

Solution & Step-by-step Explanation

Let total work be the LCM of 25 and 50, which is 50 units.
Efficiency of P =
25
50

=2 units/day
Efficiency of Q =
50
50

=1 unit/day
Total efficiency of P + Q = 2+1=3 units/day

We need to find the time taken to complete 18% of the total work:

Work to be done=18% of 50=
100
18

×50=9 units
Time taken by P and Q together:

Time=
Total efficiency
Work to be done

=
3
9

=3 days

Practice this question

Try it yourself before checking the explanation above.

P and Q can do a project in 25 and 50 days respectively. In how many days can they complete 18% of the project if they work together?
A
6 days
B
3 days
C
12 days
D
9 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion