Pannalal has done
3
1
rd of a job in 20 days, Saiprasad completes the rest of the job in 10 days. In how many days can they together do the job?
- A12 days
- B6 days
- C3 days
- D24 days
Solution & Step-by-step Explanation
Pannalal completes
3
1
of the job in 20 days.
Therefore, the total time required by Pannalal to complete the whole job alone (T
P
) is:
T
P
=20×3=60 days
The remaining work is:
1−
3
1
=
3
2
Saiprasad completes this remaining
3
2
of the job in 10 days.
Therefore, the total time required by Saiprasad to complete the whole job alone (T
S
) is:
T
S
=10×
2
3
=15 days
Let's find the time taken when they work together (T
total
):
T
total
1
=
T
P
1
+
T
S
1
T
total
1
=
60
1
+
15
1
Taking the LCM of 60 and 15, which is 60:
T
total
1
=
60
1+4
=
60
5
=
12
1
T
total
=12 days
3
1
of the job in 20 days.
Therefore, the total time required by Pannalal to complete the whole job alone (T
P
) is:
T
P
=20×3=60 days
The remaining work is:
1−
3
1
=
3
2
Saiprasad completes this remaining
3
2
of the job in 10 days.
Therefore, the total time required by Saiprasad to complete the whole job alone (T
S
) is:
T
S
=10×
2
3
=15 days
Let's find the time taken when they work together (T
total
):
T
total
1
=
T
P
1
+
T
S
1
T
total
1
=
60
1
+
15
1
Taking the LCM of 60 and 15, which is 60:
T
total
1
=
60
1+4
=
60
5
=
12
1
T
total
=12 days