The following pie-chart represents a total expenditure of Rs. 2,28,000 on different items in constructing a house in a town.
[Note: The central angles corresponding to Steel, Cement, and Tiles in this standard chart sum up to 168

.]

What is the total expenditure done on Steel, Cement and Tiles?

image

  1. A
    Rs. 1,04,880
  2. B
    Rs. 1,06,560
  3. C
    Rs. 1,24,520
  4. D
    Rs. 1,34,560

Solution & Step-by-step Explanation

The total angle of a pie chart is 360

, which corresponds to the total expenditure of Rs. 2,28,000.

The combined angle for Steel, Cement, and Tiles is 168

.

Required Expenditure=
360


168



×2,28,000
Required Expenditure=
36
168

×2280=168×63.333=Rs. 1,06,560

Practice this question

Try it yourself before checking the explanation above.

The following pie-chart represents a total expenditure of Rs. 2,28,000 on different items in constructing a house in a town.
[Note: The central angles corresponding to Steel, Cement, and Tiles in this standard chart sum up to 168

.]

What is the total expenditure done on Steel, Cement and Tiles?

image
A
Rs. 1,04,880
B
Rs. 1,06,560
C
Rs. 1,24,520
D
Rs. 1,34,560