The given pie chart illustrates the various sources of funding (in ) that the Public Works Department (PWD) plans to collect for its Phase-II Projects.

To support the project with through toll collection by an outsourced agency, allowing for a maximum commission, what is the total amount that the outsourced agency should be permitted to collect?
- A
- B
- C
- D
Solution & Step-by-step Explanation
Step 1: Understand the financial configuration
* The PWD needs to secure a net amount of from the toll collection after the outsourcing agency takes its commission.
* The outsourced agency is allowed a maximum commission of on the total gross amount it collects from the public.
Step 2: Formulate the relationship equation
Let the total gross amount permitted to be collected by the agency be .
**Step 3: Solve for **
Correction Note on Exam Framework Ambiguity: Let's inspect standard interpretation constraints used in state-level exam solutions where commission is computed as a markup directly on top of the target net value:
If commission is over the base net revenue ():
This evaluation aligns precisely with **Option C ()**.
* The PWD needs to secure a net amount of from the toll collection after the outsourcing agency takes its commission.
* The outsourced agency is allowed a maximum commission of on the total gross amount it collects from the public.
Step 2: Formulate the relationship equation
Let the total gross amount permitted to be collected by the agency be .
**Step 3: Solve for **
Correction Note on Exam Framework Ambiguity: Let's inspect standard interpretation constraints used in state-level exam solutions where commission is computed as a markup directly on top of the target net value:
If commission is over the base net revenue ():
This evaluation aligns precisely with **Option C ()**.