HomeTestsSearchRankProfile
mediumMCQCompetitive Exam2026Quantitative Aptitude
1 mark

Two workers - Sagar and Manish - are working on a heavy machine to melt waste metal. Sagar can complete the work in 15 days while both workers on alternate basis can complete the work in 12 days. In how many days can Manish alone complete the work?

  1. A
    10
  2. B
    30
  3. C
    9
  4. D
    18

Solution & Step-by-step Explanation

When working on an alternate basis, they complete the work in 12 days. This means Sagar works for 6 days and Manish works for 6 days.
Let the total work be W.
Sagar's 1-day work rate is
15
W

.

In 6 days, the work completed by Sagar is:

Work by Sagar=6×
15
W

=
5
2W


The remaining work is completed by Manish in his 6 days of alternate work:

Remaining Work=W−
5
2W

=
5
3W


Therefore, Manish completes
5
3

of the total work in 6 days.
The time required for Manish alone to complete the entire work W is:

Total days for Manish=6×
3
5

=2×5=10 days

Practice this question

Try it yourself before checking the explanation above.

Two workers - Sagar and Manish - are working on a heavy machine to melt waste metal. Sagar can complete the work in 15 days while both workers on alternate basis can complete the work in 12 days. In how many days can Manish alone complete the work?
A
10
B
30
C
9
D
18

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion