HomeTestsSearchRankProfile
mediumMCQSSC CGL2026Quantitative Aptitude
1 mark

Working separately, A and B can complete a work in 15 days and 18 days, respectively. If A starts the work and they work on alternate days, one on each day, then in how many days will the work be completed?

  1. A
    17
    3
    1

     days
  2. B
    16
    3
    1

     days
  3. C
    18
    3
    2

     days
  4. D
    15
    3
    2

     days

Solution & Step-by-step Explanation

Time taken by A=15 days
Time taken by B=18 days

Let the total work be the LCM of 15 and 18, which is 90 units.

Efficiency of A=
15
90

=6 units/day
Efficiency of B=
18
90

=5 units/day

Since they work on alternate days starting with A:
Day 1 (A) = 6 units
Day 2 (B) = 5 units

Work done in a 2-day cycle = 6+5=11 units

Number of complete 2-day cycles to get close to 90 units:

90÷11=8 cycles with a remainder of 2 units
Work done in 8 cycles (16 days) = 8×11=88 units
Remaining work = 90−88=2 units

On the 17th day, it is A's turn.
Time taken by A to complete the remaining 2 units =
Efficiency of A
Remaining Work

=
6
2

=
3
1

 day

Total time taken = 16+
3
1

=16
3
1

 days

Practice this question

Try it yourself before checking the explanation above.

Working separately, A and B can complete a work in 15 days and 18 days, respectively. If A starts the work and they work on alternate days, one on each day, then in how many days will the work be completed?
A
17
3
1

 days
B
16
3
1

 days
C
18
3
2

 days
D
15
3
2

 days

Share This Question

Related Questions

Ready for a Full Test?

Practice with timed mock tests and track your performance across Quantitative Aptitude.

Discussion