mediumSHORT_ANSWERGATE CE 2021 Question Paper (06-Feb-2021) (Shift-1)CE
2 marks

A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table.
ActivityDuration(in weeks)Depends upon
N2-
P5N
Q3N
R4P
S5Q
T8R
U7R, S
V2U
W3U
X5T, V
Y1W
Z3X, Y
The total float of the activity "V" (in weeks, in integer) is ________

Correct Answer

Solution & Step-by-step Explanation

In the range: 0 - 0

Activity Network and Calculations

To determine the total float for activity "V", we perform a Critical Path Method (CPM) analysis. This involves calculating the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), and Latest Finish (LF) for each activity.

Forward Pass (ES and EF)

The forward pass calculates the earliest possible times for starting and finishing activities.

- N: ES=0, EF = ES + Duration = 0 + 2 = 2
- P: ES=EF(N)=2, EF = 2 + 5 = 7
- Q: ES=EF(N)=2, EF = 2 + 3 = 5
- R: ES=EF(N)=2, EF = 2 + 4 = 6
- S: ES=EF(P)=7, EF = 7 + 5 = 12
- T: ES=EF(Q)=5, EF = 5 + 8 = 13
- U: ES=EF(R)=6, EF = 6 + 3 = 9
- V: ES=max(EF(R), EF(S)) = max(6, 12) = 12, EF = 12 + 2 = 14
- W: ES=EF(U)=9, EF = 9 + 3 = 12
- X: ES=EF(U)=9, EF = 9 + 5 = 14
- Y: ES=EF(T)=13, EF = 13 + 1 = 14
- Z: ES=max(EF(X), EF(Y)) = max(14, 14) = 14, EF = 14 + 3 = 17

The minimum project completion time is the maximum EF, which is 17 weeks.

Backward Pass (LF and LS)

The backward pass calculates the latest possible times activities can start and finish without delaying the project.

- Z: LF=17 (Project Duration), LS = LF - Duration = 17 - 3 = 14
- Y: LF=LS(Z)=14, LS = 14 - 1 = 13
- X: LF=LS(Z)=14, LS = 14 - 5 = 9
- W: LF=EF(W)=12 (Assuming no successors delay its LF), LS = 12 - 3 = 9
- V: LF=EF(V)=14 (Assuming no successors delay its LF), LS = 14 - 2 = 12
- T: LF=LS(Y)=13, LS = 13 - 8 = 5
- U: LF=min(LS(W), LS(X)) = min(9, 9) = 9, LS = 9 - 3 = 6
- S: LF=LS(V)=12, LS = 12 - 5 = 7
- R: LF=min(LS(U), LS(V)) = min(6, 12) = 6, LS = 6 - 4 = 2
- Q: LF=LS(T)=5, LS = 5 - 3 = 2
- P: LF=LS(S)=7, LS = 7 - 5 = 2
- N: LF=min(LS(P), LS(Q), LS(R)) = min(2, 2, 2) = 2, LS = 2 - 2 = 0

Total Float Calculation

Total Float (TF) is the amount of time an activity can be delayed without affecting the project's earliest finish time. It's calculated using the formula: or .
ActivityEF (Weeks)LF (Weeks)TF = LF - EF (Weeks)
N220
P770
Q550
R660
S12120
T13130
U990
V14140
W12120
X14140
Y14140
Z17170
For activity "V":

- Earliest Finish (EF) = 14 weeks
- Latest Finish (LF) = 14 weeks
- Total Float (TF) = LF - EF = 14 - 14 = 0 weeks.

Alternatively, using LS and ES:

- Earliest Start (ES) = 12 weeks
- Latest Start (LS) = 12 weeks
- Total Float (TF) = LS - ES = 12 - 12 = 0 weeks.

The total float for activity "V" is 0 weeks.

Practice this question

Try it yourself before checking the explanation above.

A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table.
ActivityDuration(in weeks)Depends upon
N2-
P5N
Q3N
R4P
S5Q
T8R
U7R, S
V2U
W3U
X5T, V
Y1W
Z3X, Y
The total float of the activity "V" (in weeks, in integer) is ________

Share This Question

Related Questions

mediumSHORT_ANSWER

The state of stress in a deformable body is shown in the figure. Consider transformation of the stress from the x-y coordinate system to the X-Y coordinate system. The angle θ , locating the X-axis, is assumed to be positive when measured from the x-axis in counter-clockwise direction. ![image](https://cdn.prepp.in/uploads/production/images/content/2026_01_22/image_7805f2981769107953674.png) The absolute magnitude of the shear stress component σ_xy (in MPa, round off to one decimal place) in x-y coordinate system is ________

mediumMCQ

Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which Contractor X has competed against Contractor Y is given in the Table Ratio of Y's bid price to X's cost, Number of bids. 1.02, 6. 1.04, 12. 1.06, 3. 1.10, 6. 1.12, 3 Based on the bidding behaviour of the Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is

mediumMCQ

If P = 1 & 2 \\3 & 4 and Q = 0 & 1 \\1 & 0 then Q^T P^T is

mediumMCQ

The shape of the most commonly designed highway vertical curve is

mediumSHORT_ANSWER

The cohesion (c), angle of internal friction ( ) and unit weight ( γ ) of a soil are 15kPa, 20^ and 17.5 kN/m^3 , respectively. The maximum depth of unsupported excavation in the soil (in m, round off to two decimal places) is ________

mediumSHORT_ANSWER

A retaining wall of height 10 m with clay backfill is shown in the figure (not to scale). Weight of the retaining wall is 5000 kN per m acting at 3.3 m from the toe of the retaining wall. The interface friction angle between base of the retaining wall and the base soil is 20^ . The depth of clay in front of the retaining wall is 2.0 m. The properties of the clay backfill and the clay placed in front of the retaining wall are the same. Assume that the tension crack is filled with water. Use Rankine's earth pressure theory. Take unit weight of water, γ_w = 9.81 kN/m ^3 . ![image](https://cdn.prepp.in/uploads/production/images/content/2026_01_22/image_1d0de8a21769109336565.png) The factor of safety (round off to two decimal places) against sliding failure of the retaining wall after ignoring the passive earth pressure will be ________

Ready for a Full Test?

Practice with timed mock tests and track your performance across CE.

Discussion