Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which Contractor X has competed against Contractor Y is given in the Table
Ratio of Y's bid price to X's costNumber of bids
1.026
1.0412
1.063
1.106
1.123
Based on the bidding behaviour of the Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is

  1. A
    0%
  2. B
    more than 0% but less than 50%
  3. C
    more than 50% but less than 100%
  4. D
    100%

Solution & Step-by-step Explanation

Contractor X Bidding Strategy Analysis

This solution calculates the probability of Contractor X winning a bid against Contractor Y, using historical bid data and a specific markup strategy.

Historical Bid Data Summary

The table provides the frequency distribution of the ratio for 30 previous bids:
Ratio (Y's Bid Price / X's Cost)Number of Bids
1.026
1.0412
1.063
1.106
1.123
The total number of bids analyzed is .

Determining the Winning Condition

Contractor X plans to use an 8% markup. Contractor X's bid price is calculated as:



Contractor X wins if their bid price is less than Contractor Y's bid price:



Substituting the formula for X's bid price:



To determine the winning condition based on the provided ratio, we rearrange the inequality:



This means Contractor X wins if the ratio of Y's bid price to X's cost is greater than 1.08.

Probability Calculation Steps

We count the historical bids where the ratio was greater than 1.08:

- Ratio = 1.10: 6 bids
- Ratio = 1.12: 3 bids

The total number of bids where Contractor X would have won is .

The probability of winning is the number of winning bids divided by the total number of bids:





or 30%

Result and Conclusion

The calculated probability of Contractor X winning the next bid with an 8% markup is 30%.

Comparing this probability to the given options:

- 0%
- more than 0% but less than 50%
- more than 50% but less than 100%
- 100%

Since 30% is greater than 0% and less than 50%, Option 2 is the correct range.

Practice this question

Try it yourself before checking the explanation above.

Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which Contractor X has competed against Contractor Y is given in the Table
Ratio of Y's bid price to X's costNumber of bids
1.026
1.0412
1.063
1.106
1.123
Based on the bidding behaviour of the Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is
A
0%
B
more than 0% but less than 50%
C
more than 50% but less than 100%
D
100%

Share This Question

Related Questions

mediumSHORT_ANSWER

The state of stress in a deformable body is shown in the figure. Consider transformation of the stress from the x-y coordinate system to the X-Y coordinate system. The angle θ , locating the X-axis, is assumed to be positive when measured from the x-axis in counter-clockwise direction. ![image](https://cdn.prepp.in/uploads/production/images/content/2026_01_22/image_7805f2981769107953674.png) The absolute magnitude of the shear stress component σ_xy (in MPa, round off to one decimal place) in x-y coordinate system is ________

mediumSHORT_ANSWER

A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y, and Z. The relationship among these activities and the duration of these activities are given in the Table. Activity, Duration(in weeks), Depends upon. N, 2, -. P, 5, N. Q, 3, N. R, 4, P. S, 5, Q. T, 8, R. U, 7, R, S. V, 2, U. W, 3, U. X, 5, T, V. Y, 1, W. Z, 3, X, Y The total float of the activity "V" (in weeks, in integer) is ________

mediumMCQ

If P = 1 & 2 \\3 & 4 and Q = 0 & 1 \\1 & 0 then Q^T P^T is

mediumMCQ

The shape of the most commonly designed highway vertical curve is

mediumSHORT_ANSWER

The cohesion (c), angle of internal friction ( ) and unit weight ( γ ) of a soil are 15kPa, 20^ and 17.5 kN/m^3 , respectively. The maximum depth of unsupported excavation in the soil (in m, round off to two decimal places) is ________

mediumSHORT_ANSWER

A retaining wall of height 10 m with clay backfill is shown in the figure (not to scale). Weight of the retaining wall is 5000 kN per m acting at 3.3 m from the toe of the retaining wall. The interface friction angle between base of the retaining wall and the base soil is 20^ . The depth of clay in front of the retaining wall is 2.0 m. The properties of the clay backfill and the clay placed in front of the retaining wall are the same. Assume that the tension crack is filled with water. Use Rankine's earth pressure theory. Take unit weight of water, γ_w = 9.81 kN/m ^3 . ![image](https://cdn.prepp.in/uploads/production/images/content/2026_01_22/image_1d0de8a21769109336565.png) The factor of safety (round off to two decimal places) against sliding failure of the retaining wall after ignoring the passive earth pressure will be ________

Ready for a Full Test?

Practice with timed mock tests and track your performance across CE.

Discussion