A and B can complete a piece of work in 10 days. B and C can do it in 15 days. A and C can do it in 12 days. A, B and C together can complete it in how many days?
Some workers could complete a work in 150 days. However, due to the absence of 15 workers it was completed in 165 days. Then the initial number of workers was:
A laboratory has to pay Rs. 67.50 for 30 days as a gas bill if it uses 35 gas burners for 6hours a day. Find the amount to be paid if it uses 30 gas burners for 18 days working 7hours a day.
A and B together can do a piece of work in 25 days. If B works alone for the last 10 days, it is completed in 30 days. In how many days can A alone do it?
If 50 men do a piece of work in 12 days working 8hours a day, how many hours a day would 60 men have to work in order to do another piece of work twice as great in 16 days?
The cost of printing a magazine of 540 pages with 30 lines on each page and 15 words in each line is Rs. 7200. Find the cost of printing a magazine of 450 pages with 35 lines on each page and 18 words in each line.
A contractor undertook to finish a road 12km long in 350 days. But after employing 45 men for 200 days, he found that only 4km of the road had been built. How many additional men must be engaged to finish the work in the given time?
A man and a boy can do a piece of work in 36 days. If the man works alone for the last 10 days, the work is completed in 40 days. How long would the boy take to do it alone?
Ramen deposits Rs. 100 on the first day of every month in a monthly savings scheme. In this way, he has deposited money for 1 year. If the rate of simple interest is 6% per annum, then the total amount he will get at the end of the year is
X and Y can complete a work in 12 days and 18 days respectively. They started doing the work together but after 4 days Y had to leave and X alone completed the remaining work. In how many days was the whole work completed?
A garrison of 140 men has provisions for 35 days. At the end of 10 days, 35 more men joined them. How many days can they sustain on the remaining provisions?
A group of men decided to complete a job in 4 days. However, since 10 men dropped out every day, the job got completed at the end of the 7th day. How many men were there in the beginning?
A and B can do a work in 13 days and 26 days, respectively. If they work for a day alternately, starting with A, then in how many days will the work be completed?
Competitive Exams Time and Work — FAQ
How many Time and Work questions come in Competitive Exams?▼
Our database has 18 Time and Work questions from Competitive Exams covering 2026 to 2026.
What difficulty are Competitive Exams Time and Work questions?▼
The 18 Competitive Exams Time and Work questions include 0 easy, 18 medium and 0 hard level questions.