112 Time and Work questions from Competitive Exam with detailed answers and explanations. Free previous year questions and MCQs.

📚
112
Questions
🟢
3
Easy
🟡
108
Medium
🔴
1
Hard
Years:2026 (112)

Time and WorkCompetitive Exam(1100 of 112)

Filter:
Q1mediummcqQuantitative AptitudeCompetitive Exam2026
7% accuracy
A, B and C can do the same work in 9 days, 12 days and 18 days, respectively. A started the work and worked for 3 days and left. Then, B joined the work and worked for 3 days and left. Then, C joined the work and completed the work. Find the number of days C took to complete the work.
Q2mediummcqQuantitative AptitudeCompetitive Exam2026
25% accuracy
A, B and C can do one-third of a work in 15 days, 30 days and 10 days, respectively. A started the work. C joined him after 1 day and B joined them after 3 days of the beginning. For how many days did C work?
Q3mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
A is 40% more efficient than B. If B finishes a work in 14 days, then in how many days will A finish the same work?
Q4mediummcqQuantitative AptitudeCompetitive Exams2026
0% accuracy
Some workers could complete a work in days. However, due to the absence of workers it was completed in days. Then the initial number of workers was:
Q5hardmcqQuantitative AptitudeCompetitive Exam Practice2026
0% accuracy
Suppose every three adults consume 2 litres of milk and 0.5 kg sugar every day, and the daily consumption of every five children is double the milk and half of the sugar than what the three adults consume. A family has 5 adults and 8 children. Their expenditure on milk and sugar for a month of 30 days, if a half-litre milk packet costs Rs. 25 and a one kg sugar packet costs Rs. 80, is:
Q6mediummcqQuantitative AptitudeCompetitive Exam Practice2026
33% accuracy
A can finish a task in days and B can finish the same task in half the time taken by A. Working together, what part of the task can they finish in a day?
Q7easymcqQuantitative AptitudeCompetitive Exam Practice2026
0% accuracy
Rahul can complete a work in 12 days and Ayush in 15 days. If they work together for 3 days, then the fraction of work that will be left is:
Q8mediummcqQuantitative AptitudeCompetitive Exams2026
0% accuracy
A and B can complete a piece of work in days. B and C can do it in days. A and C can do it in days. A, B and C together can complete it in how many days?
Q9mediummcqQuantitative AptitudeCompetitive Exam 20262026
0% accuracy
30 persons working 10 hours a day can do 5 units of work in 12 days. How many people are required to do 8 units of that work in 16 days if they work for 8 hours a day?
Q10mediummcqQuantitative AptitudeCompetitive Exam 20262026
33% accuracy
If 12 students can read 4800 pages of a book in 15 days, then how many students can read 7200 pages of the same book in 10 days?
Q11mediummcqQuantitative AptitudeCompetitive Exam Practice2026
0% accuracy
In a typing shop, Lalit can complete typing of a book in 9 days, while Amit can finish the same work in 8 days. How many days will they take together to complete the work?
Q12mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
120 men consume 720kg of rice in 30 days. In how many days can 90 men consume 270kg?
Q13mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
A and B can together complete a task in 40 days. They worked together for 30 days and then B left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?
Q14mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
A and B can complete a task in 40 days and 16 days respectively. A started the task alone and then after 12 days B joined him till the completion of the task. How long did the task last after B joined the task?
Q15mediummcqQuantitative AptitudeCompetitive Exam2026
50% accuracy
men and women can do a work in days. men and women can do the same work in days. If men and women together do the same work, in how many days will they complete the work?
Q16mediummcqQuantitative AptitudeCompetitive Exam2026
50% accuracy
Indian Railways employed workers to complete a certain work in days. If only one-fourth of the work had been done in days, then to complete the whole work in time, what is the number of additional workers to be employed?
Q17mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
An AC can cool a hall in 10min, while an AC of another brand can cool the same hall in 15min. If both the ACs are switched on at the same time, then in how much time will they cool the hall?
Q18mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
A can do a piece of work in 63 days and B is more efficient than A. Then the number of days taken by B to do the same work is:
Q19mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
men can do a work in days. Find the amount of work done by men in days.
Q20mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
Ramu can build a wall alone in , while Ravan can build it alone in . Ramu worked for . Then Ravan joined Ramu for the next . How many more days could Ramu take to build the remaining wall?
Q21mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
A person can paint a 2.5ft
2
of a wall in 5 minutes. How much ft
2
of the wall will he paint in 6 hours?
Q22mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
If 6 people are required to complete a work in 1 hour 20 minutes, then how long will only 5 people take to complete the same work?
Q23mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
A can finish as much work in 6 days as C can in 8 days. B can finish as much work in 6 days as C can in 4 days. How much time will B require to finish a work if A takes 54 days to finish it?
Q24mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
persons can repair a tunnel in days working hours a day. In how many days will persons working hours a day complete the work?
Q25mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
40 men can complete a work in 15 days. Five days after they started working, 10 more men joined them. In how many days will the total work be completed?
Q26mediummcqQuantitative AptitudeCompetitive Exam2026
0% accuracy
Raj can build a house in 16 days by himself, while Suraj can do it in 12 days. Raj and Suraj work on alternate days. How many days would the house take to build if Raj starts working on the first day?
Q27mediummcqQuantitative AptitudeCompetitive Exam2026
A takes 84 hours to finish a work. B completes the same work in one-fourth of the time taken by A. What fraction of work will they complete in 12 hours?
Q28mediummcqQuantitative AptitudeCompetitive Exam2026
If 72 boys can build a wall of length in 21 days, how many boys would take 18 days to build a similar type of wall of length ?
Q29mediummcqQuantitative AptitudeCompetitive Exam2026
A can complete a piece of work in 12 days while B can do the same work in 18 days. If they both work together, then how many days will be required to finish the work?
Q30mediummcqQuantitative AptitudeCompetitive Exam2026
By working 12 hours a day, 90 people can complete a work in 16 days. How much work will be left after 24 days if 70 people work for 8 hours per day?
Q31mediummcqQuantitative AptitudeCompetitive Exam2026
The average time taken by 6 athletes in a race is 1 minute 50 seconds. The winner completed the race in 1 minute 20 seconds. What is the average time taken by the other 5 athletes?
Q32mediummcqQuantitative AptitudeCompetitive Exam2026
P works twice as fast as Q. If Q can complete a task in 36 days independently, the number of days in which P and Q can together complete the task is:
Q33mediummcqQuantitative AptitudeCompetitive Exam2026
If persons build a wall in days, then how many persons will be required to build the same type of wall of length in days?
Q34mediummcqQuantitative AptitudeCompetitive Exam2026
A can finish a work in 15 days and B can do the same work in twice the time taken by A. Then, working together, what part of the same work they can finish in five days?
Q35mediummcqQuantitative AptitudeCompetitive Exam2026
If 7 men and 4 women working together can do five times as much work per hour as one man and one woman together, then the ratio of the work done by a man and that of a woman for a given time is:
Q36mediummcqQuantitative AptitudeCompetitive Exam2026
C and B can do a work in days and days respectively. They worked together for days and then C left. In how many days did B finish the remaining work?
Q37mediummcqQuantitative AptitudeCompetitive Exam2026
A tank is normally filled in 18 hours by a pipe, but it takes 6 hours more to fill the tank due to a leakage at its bottom. The leakage point can empty the tank when it is two-third full in ______ hours.
Q38mediummcqQuantitative AptitudeCompetitive Exam2026
When working hours per day, Anvita alone can complete a piece of work in days and Maya alone can complete it in days. If they work together for hours per day, in how many days will they complete the work?
Q39mediummcqQuantitative AptitudeCompetitive Exam2026
Komal can do a work in days. Bimal is more efficient than Komal in doing the work. In how many days will Bimal do that work?
Q40mediummcqQuantitative AptitudeCompetitive Exam2026
Reena and Riya together can complete a piece of work in 36 days. Riya and Geeta together can complete it in 54 days. Reena and Geeta together can complete it in 81 days. In how many days can Reena alone complete the work?
Q41mediummcqQuantitative AptitudeCompetitive Exam2026
A can do a piece of work in 12 days, and B can do the same work in 15 days. With the help of C, they can finish the work in 5 days. How long will it take C to finish the work?
Q42mediummcqQuantitative AptitudeCompetitive Exam2026
Akash is 3 times as good a workman as Baldev and therefore is able to finish a job in 40 days less than Baldev. Working together, they can finish it in ________.
Q43mediummcqQuantitative AptitudeCompetitive Exam2026
A can do a piece of work in and B is more efficient than A. Then the number of days taken by B to do the same work is:
Q44mediummcqQuantitative Aptitude@NUM: 70Competitive Exam2026
If men and women working together can do six times as much work per hour as man and women working together, then the ratio of the work done by man to that of woman in a given time is:
Q45mediummcqQuantitative AptitudeCompetitive Exams2026
A garrison of 140 men has provisions for 35 days. At the end of 10 days, 35 more men joined them. How many days can they sustain on the remaining provisions?
Q46mediummcqQuantitative AptitudeCompetitive Exam2026
A does 75% of a work in 45 days. He then calls in B and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?
Q47mediummcqQuantitative AptitudeCompetitive Exam2026
A is half as efficient as B who is thrice as efficient as C. In how many days can all of them complete a task if B can complete the task alone in days?
Q48mediummcqQuantitative AptitudeCompetitive Exam Practice2026
A and B can do a work in 15 days and 30 days, respectively. They start working together, but A leaves after 3 days. How much time will B take to complete the remaining work?
Q49mediummcqQuantitative AptitudeCompetitive Exam2026
A and B can complete a task in days, B and C can complete the task in days, A and C can complete the task in days. In how many days will they together complete the task?
Q50mediummcqQuantitative AptitudeCompetitive Exam2026
A is twice as good a workman as B. A and B together complete a piece of work in days. In how many days will A alone do the same piece of work?
Q51mediummcqQuantitative AptitudeCompetitive Exam2026
A and B each can do a work in days. They began the work together but A left after some time and B completed the remaining work in days. After how many days of the start of the work did A leave?
Q52mediummcqQuantitative AptitudeCompetitive Exam2026
A single person takes minutes to fill a bottle. If from 11 am to 12.30 pm bottles are to be filled, how many persons should be employed on this job?
Q53mediummcqQuantitative AptitudeCompetitive Exam2026
Pipes A and B can fill a tank in hours and hours, respectively, whereas pipe C alone can empty the full tank in hours. When all the pipes are opened together, the tank is full in hours. What is the value of ?
Q54mediummcqQuantitative AptitudeCompetitive Exam2026
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take:
Q55mediummcqQuantitative AptitudeCompetitive Exams2026
Ramen deposits on the first day of every month in a monthly savings scheme. In this way, he has deposited money for year. If the rate of simple interest is per annum, then the total amount he will get at the end of the year is
Q56mediummcqQuantitative AptitudeCompetitive Exam2026
ladies can do a job in days. Due to some reason, some ladies did not join the work and therefore, it was completed in days. The number of ladies who did not join the work is
Q57mediummcqQuantitative AptitudeCompetitive Exam2026
If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?
Q58mediummcqQuantitative AptitudeCompetitive Exams2026
A man and a boy can do a piece of work in days. If the man works alone for the last days, the work is completed in days. How long would the boy take to do it alone?
Q59mediummcqQuantitative AptitudeCompetitive Exam2026
2 men and 1 woman together can complete a piece of work in 14 days. 4 women and 2 men together can do it in 8 days. If a man gets ₹600 per day, how much should a woman get per day?
Q60mediummcqQuantitative AptitudeCompetitive Exams2026
A contractor undertook to finish a road long in days. But after employing men for days, he found that only of the road had been built. How many additional men must be engaged to finish the work in the given time?
Q61easymcqQuantitative AptitudeCompetitive Exam2026
A and B can complete a piece of work in 25 days and 55 days, respectively. The total number of days (in whole number) to complete the work, if A and B both work together, is:
Q62mediummcqQuantitative AptitudeCompetitive Exam2026
If 28 men can do a piece of work in 26 days, then in how many days 13 men will do it?
Q63mediummcqQuantitative AptitudeCompetitive Exam2026
X, Y and Z can do a piece of work in 4 days, 5 days and 7 days, respectively. They get Rs. 415 for completing the work. If X, Y and Z have worked together to complete the work, what is X's share?
Q64mediummcqQuantitative AptitudeCompetitive Exam2026
X, Y and Z can complete a piece of work in 8, 20 and 25 days respectively. Working together, they will complete the same work in:
Q65mediummcqQuantitative AptitudeCompetitive Exam2026
A can do three-seventh of a work in days and B can do two-fifth of the same work in days. If A and B work together, then how long (in days) will they take to complete the work?
Q66mediummcqQuantitative AptitudeCompetitive Exam2026
10 men and 8 women can do a piece of work in 7
2
1

days whereas 6 men and 9 women can do the same work in 10 days. In how many days will 35 women complete the same work?
Q67mediummcqQuantitative AptitudeCompetitive Exam2026
A and B complete a work in 12 and 15 days, respectively. They started the work alternatively for 1 day each and A started the work first. In how much time will 60% of the work be completed?
Q68mediummcqQuantitative AptitudeCompetitive Exam2026
Two workers - Sagar and Manish - are working on a heavy machine to melt waste metal. Sagar can complete the work in 15 days while both workers on alternate basis can complete the work in 12 days. In how many days can Manish alone complete the work?
Q69mediummcqQuantitative AptitudeCompetitive Exam2026
A can complete 40% of a work in 6 days and B can complete 33
3
1

% of the same work in 8 days. They work together for 8 days. C alone completes the remaining work in 4 days. A and C together will complete the same work in:
Q70mediummcqQuantitative AptitudeCompetitive Exam2026
A can complete 25% of the work in 4 days, B can complete 50% of the same work in 12 days and C can complete the same work in 32 days. They started working together but C left after 4 days of the start and A left 6 days before the completion of the work. In how many days was the work completed?
Q71mediummcqQuantitative AptitudeCompetitive Exam2026
A and B can do a piece of work separately in 10 days and 8 days, respectively. If they work alternately and A begins the work, in how many days will the work be completed?
Q72mediummcqQuantitative AptitudeCompetitive Exam2026
Aman and Rajan are working at a construction site. In some engineering experiment, Aman is constructing a wall, while Rajan is demolishing that wall. Aman can completely build the wall in 15 days, while Rajan will take 20 days to completely demolish the wall. In how many days will the complete wall be built for the first time if they work on alternate days, with Aman working on the 1
st
day?
Q73mediummcqQuantitative AptitudeCompetitive Exam2026
A machine can complete double the work that a man can complete in a given period of time. To complete a work, 10 machines and 5 men take 60 days. If there were 10 men and 5 machines, then the time it would have taken to complete the work is:
Q74mediummcqQuantitative AptitudeCompetitive Exam2026
4 men and 4 women can complete a work in 5 days, while 2 men and 5 women can finish it in 6 days. How much time (in days) will be taken by 1 woman working alone and 1 man working all by himself to complete the work, respectively?
Q75mediummcqQuantitative AptitudeCompetitive Exam2026
How many workers would be needed to complete the same task in 6 days if it takes 10 days for 15 workers to complete a task ?
Q76mediummcqQuantitative AptitudeCompetitive Exam2026
A completes a work in 3 days while B completes it in 6 days. If they work alternately with A starting work first, then in how many days will the work be finished?
Q77mediummcqQuantitative AptitudeCompetitive Exam2026
A, B and C can complete a work in , and days respectively. In how many days can A, B and C together do of the same work?
Q78mediummcqQuantitative AptitudeCompetitive Exam2026
A can finish one-third of a work in 5 days, and B can finish 50% of the same work in 15 days. If they work together, then in how many days will they finish 50% of the work?
Q79mediummcqQuantitative AptitudeCompetitive Exam2026
persons can repair a tunnel in days working hours a day. In how many days will persons working hours a day complete the work?
Q80mediummcqQuantitative AptitudeCompetitive Exams2026
At a construction site, 15 men or 10 machines can construct a room in 66 days. In how many days can 5 men and 4 machines together complete the work?
Q81mediummcqQuantitative AptitudeCompetitive Exam2026
In the first 44 overs of a cricket match, the run rate was 5.1runs/over. Calculate the required run rate in the remaining 6 overs to reach the target of 294 runs?
Q82mediummcqQuantitative AptitudeCompetitive Exams2026
and can do a work in days and days, respectively. If they work for a day alternately, starting with , then in how many days will the work be completed?
Q83mediummcqQuantitative AptitudeCompetitive Exam2026
Three pipes can fill a tank in 15 hours, 12 hours and 10 hours, respectively. If all the three pipes are opened simultaneously for 3 hours, then what percentage of the tank will remain unfilled?
Q84mediummcqQuantitative AptitudeCompetitive Exams2026
X and Y can complete a work in 12 days and 18 days respectively. They started doing the work together but after 4 days Y had to leave and X alone completed the remaining work. In how many days was the whole work completed?
Q85easymcqQuantitative AptitudeCompetitive Exam2026
If 108 workers can build a wall in 36 days, then in how many days can 48 workers build the same wall?
Q86mediummcqQuantitative AptitudeCompetitive Exam2026
B & C can complete a task in days while A, B & C can complete the task in days. In how many days can A complete the task alone?
Q87mediummcqQuantitative Aptitude@NUM: 56Competitive Exam2026
A, B and C can complete a certain work in , and days, respectively. A and B together start the work and B leaves after working for days. A and C together will complete the remaining work in ______ days.
Q88mediummcqQuantitative AptitudeIndian Competitive Exam Prep2026
In a military camp, there was sufficient food for days for a total of men. After days, men left the camp. The remaining men will spend the remaining food provisions in how many days?
Q89mediummcqQuantitative AptitudeCompetitive Exam Practice2026
Eight labourers working 10 hours a day completed a work in 18 days. If only 5 labourers are working, then in how many hours a day should they work to finish the work in 24 days?
Q90mediummcqMathematicsCompetitive Exam2026
A pump can fill a tank with water in hours. Due to leakage in the bottom, it takes hours to fill it. In what time will the leak empty the fully filled tank?
Q91mediummcqQuantitative AptitudeCompetitive Exam2026
men or women can do a piece of work in days. The number of days needed to complete the job, if men and women are employed to do the same piece of work is:
Q92mediummcqQuantitative AptitudeCompetitive Exam2026
A frog was at the bottom of an 80m deep well. It attempted to come out of it by jumping. In each jump, it covered 1.15m but slipped down by 0.75m. The number of jumps after which it would be out of the well is:
Q93mediummcqQuantitative AptitudeCompetitive Exam2026
and can do a piece of work in days, and in days, and and in days. The number of days taken by , , and working together to finish the work is
Q94mediummcqQuantitative AptitudeCompetitive Exam2026
A can do three-fourth of a work in 12 days and B can do four-fifth of the same work in 20 days. In how many days can they complete the whole work, working together?
Q95mediummcqQuantitative AptitudeCompetitive Exam2026
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3:2. In how many days can the faster person complete the job?
Q96mediummcqMathematicsCompetitive Exam2026
Komal can do a work in days. Bimal is more efficient than Komal in doing the work. In how many days Bimal will do that work?
Q97mediummcqMathematicsCompetitive Exam2026
How many workers would be needed to complete the same task in days if it takes days for workers to complete a task?
Q98mediummcqQuantitative AptitudeCompetitive Exam2026
A and B can complete a work in days and days respectively. Both work for days and then A leaves. Find how much time will B take to complete the remaining work?
Q99mediummcqQuantitative AptitudeSSC Competitive Exams2026
A group of men decided to complete a job in 4 days. However, since 10 men dropped out every day, the job got completed at the end of the 7th day. How many men were there in the beginning?
Q100mediummcqQuantitative AptitudeCompetitive Exam2026
If men can build a wall of length in days, then how many men are required to build the same wall of length in days?

Competitive Exam Time and Work — FAQ

How many Time and Work questions come in Competitive Exam?
Our database has 112 Time and Work questions from Competitive Exam covering 2026 to 2026.
What difficulty are Competitive Exam Time and Work questions?
The 112 Competitive Exam Time and Work questions include 3 easy, 108 medium and 1 hard level questions.