HomeTestsSearchRankProfile

Time And Work Questions

Practice 227 Time And Work questions with detailed answers and explanations. Free MCQs, PYQs, and mock test questions for NEET, JEE, GATE, SSC and more.

📚
227
Total Questions
🟢
12
Easy
🟡
209
Medium
🔴
6
Hard

Page 2 of 3(101200 of 227)

3 pages
Filter:
Q101mediummcqQuantitative AptitudeCompetitive Exams2026
X and Y can complete a work in 12 days and 18 days respectively. They started doing the work together but after 4 days Y had to leave and X alone completed the remaining work. In how many days was the whole work completed?
Q102mediummcqQuantitative AptitudeCompetitive Exam Practice2026
Eight labourers working 10 hours a day completed a work in 18 days. If only 5 labourers are working, then in how many hours a day should they work to finish the work in 24 days?
Q103mediummcqQuantitative AptitudePractice Test2026
A contractor undertakes to make a tunnel in days and employs men. After days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work days earlier?
Q104mediummcqQuantitative AptitudeSSC CGL2026
Pannalal has done
3
1

rd of a job in 20 days, Saiprasad completes the rest of the job in 10 days. In how many days can they together do the job?
Q105mediummcqQuantitative AptitudeCompetitive Exam2026
A frog was at the bottom of an 80m deep well. It attempted to come out of it by jumping. In each jump, it covered 1.15m but slipped down by 0.75m. The number of jumps after which it would be out of the well is:
Q106easymcqQuantitative AptitudeStaff Selection Commission2026
women do half of the total work in days. How many more women will be required to complete the remaining work in days?
Q107mediummcqQuantitative AptitudeSSC CGL2026
Parimal has done
4
1

th of a job in 10 days, Salim completes the rest of the job in 20 days. In how many days can they together do the job?
Q108mediummcqQuantitative AptitudeCompetitive Exam2026
Pipes A and B can fill a tank in hours and hours, respectively, whereas pipe C alone can empty the full tank in hours. When all the pipes are opened together, the tank is full in hours. What is the value of ?
Q109mediummcqQuantitative AptitudeCompetitive Exam2026
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3:2. In how many days can the faster person complete the job?
Q110mediummcqQuantitative AptitudeSSC CGL2026
Prabodh has done 1/2 of a job in 30 days, Sapan completes the rest of the job in 45 days. In how many days can they together do the job?
Q111mediummcqQuantitative AptitudeUP Police Constable2026
A takes more time to complete a work than B. If together they take to complete the work, how much time shall B take to do it alone?
Q112mediummcqQuantitative AptitudeSSC CGL2026
The ratio of efficiencies of and for doing a certain work is . Working together they can complete the work in days. alone will complete of that work in:
Q113mediummcqQuantitative AptitudeCompetitive Exam2026
A is half as efficient as B who is thrice as efficient as C. In how many days can all of them complete a task if B can complete the task alone in days?
Q114mediummcqQuantitative AptitudeSSC CGL2026
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?
Q115mediummcqMathematicsCompetitive Exam2026
Komal can do a work in days. Bimal is more efficient than Komal in doing the work. In how many days Bimal will do that work?
Q116mediummcqQuantitative AptitudeCompetitive Exam2026
A and B each can do a work in days. They began the work together but A left after some time and B completed the remaining work in days. After how many days of the start of the work did A leave?
Q117hardmcqQuantitative AptitudeSSC Selection Post 2021 Matriculation Level2026
A tap can fill a tank in 6 hours. After 4 hours it was found that only 60% of the tank is full due to a leakage at the bottom which was then immediately repaired. In how much time will the tank be completely filled?
Q118easymcqQuantitative AptitudeCompetitive Exam2026
A and B can complete a piece of work in 25 days and 55 days, respectively. The total number of days (in whole number) to complete the work, if A and B both work together, is:
Q119mediummcqQuantitative Aptitude@NUM: 59SSC CGL2026
A can do of a work in days, and B can do of that work in days. They worked together for days and then A left the work. B alone will complete the remaining work in how many days?
Q120mediummcqQuantitative AptitudeCompetitive Exam2026
A and B can complete a task in days, B and C can complete the task in days, A and C can complete the task in days. In how many days will they together complete the task?
Q121mediummcqQuantitative AptitudeCompetitive Exam2026
If 28 men can do a piece of work in 26 days, then in how many days 13 men will do it?
Q122mediummcqQuantitative AptitudeCompetitive Exam2026
A and B complete a work in 12 and 15 days, respectively. They started the work alternatively for 1 day each and A started the work first. In how much time will 60% of the work be completed?
Q123mediummcqQuantitative AptitudeSSC CGL2026
P and Q can do a project in 25 and 50 days respectively. In how many days can they complete 18% of the project if they work together?
Q124mediummcqQuantitative AptitudePractice Test2026
Anita and Anand can complete a work in 12 days and 18 days respectively. They undertook to complete that work for ₹48,000. With the help of Arun, they completed the work in 6 days. Find the sum of the shares of Anita and Anand (in ₹).
Q125easymcqQuantitative AptitudeSSC CGL2026
A group of 25 tourists consume 5 containers of food in 8 days in a hotel. How many containers will be required for 10 tourists to eat for 16 days?
Q126mediummcqQuantitative AptitudeCompetitive Exam2026
A can complete 40% of a work in 6 days and B can complete 33
3
1

% of the same work in 8 days. They work together for 8 days. C alone completes the remaining work in 4 days. A and C together will complete the same work in:
Q127mediummcqQuantitative AptitudeAdda2472026
If boys can build a wall of length in days, how many boys would take days to build a similar type of wall of length ?
Q128mediummcqQuantitative AptitudeCompetitive Exam2026
Aman and Rajan are working at a construction site. In some engineering experiment, Aman is constructing a wall, while Rajan is demolishing that wall. Aman can completely build the wall in 15 days, while Rajan will take 20 days to completely demolish the wall. In how many days will the complete wall be built for the first time if they work on alternate days, with Aman working on the 1
st
day?
Q129mediummcqQuantitative AptitudeCompetitive Exam2026
A can complete 25% of the work in 4 days, B can complete 50% of the same work in 12 days and C can complete the same work in 32 days. They started working together but C left after 4 days of the start and A left 6 days before the completion of the work. In how many days was the work completed?
Q130mediummcqQuantitative AptitudeIndian Competitive Exam Prep2026
In a military camp, there was sufficient food for days for a total of men. After days, men left the camp. The remaining men will spend the remaining food provisions in how many days?
Q131mediummcqQuantitative AptitudeCompetitive Exam2026
A can do three-seventh of a work in days and B can do two-fifth of the same work in days. If A and B work together, then how long (in days) will they take to complete the work?
Q132mediummcqQuantitative AptitudeCompetitive Exam2026
A takes 84 hours to finish a work. B completes the same work in one-fourth of the time taken by A. What fraction of work will they complete in 12 hours?
Q133mediummcqQuantitative AptitudeCompetitive Exam2026
A can finish a work in 15 days and B can do the same work in twice the time taken by A. Then, working together, what part of the same work they can finish in five days?
Q134mediummcqQuantitative AptitudeCompetitive Exam2026
X, Y and Z can complete a piece of work in 8, 20 and 25 days respectively. Working together, they will complete the same work in:
Q135mediummcqQuantitative AptitudeUP Police Constable Re-Exam2026
and each can do a work in . They began the work together but left after some time and completed the remaining work in . After how many days of the start of the work did leave?
Q136mediummcqQuantitative AptitudeCompetitive Exam2026
A is twice as good a workman as B. A and B together complete a piece of work in days. In how many days will A alone do the same piece of work?
Q137mediummcqQuantitative AptitudeStaff Selection Commission2026
Pipes A and B can fill a tank in 18 hours and 27 hours, respectively, whereas pipe C can empty the full tank in 54 hours. All three pipes are opened together, but pipe C is closed after 12 hours. In how much time (in minutes) will the one-third of the remaining part of the tank be filled by A and B together?
Q138mediummcqQuantitative AptitudeCompetitive Exam2026
4 men and 4 women can complete a work in 5 days, while 2 men and 5 women can finish it in 6 days. How much time (in days) will be taken by 1 woman working alone and 1 man working all by himself to complete the work, respectively?
Q139mediummcqQuantitative AptitudeStaff Selection Commission2026
3 men can finish a work in 10 days, 4 women can finish it in 12 days and 10 qualified workers can finish it in 6 days. In how many days is the work finished by 4 men, 4 women and 4 qualified workers, working together every day?
Q140mediummcqQuantitative AptitudePractice Test2026
A group of workers can complete a job in days. If each worker is paid per day, what is the total wage paid to all workers?
Q141mediummcqQuantitative AptitudePractice Test2026
Manav and Manu can complete a piece of work in days and days, respectively. They worked together for days, after which Manav leaves. In how many days can Manu finish the remaining work?
Q142mediummcqQuantitative AptitudeCompetitive Exam2026
Three pipes can fill a tank in 15 hours, 12 hours and 10 hours, respectively. If all the three pipes are opened simultaneously for 3 hours, then what percentage of the tank will remain unfilled?
Q143mediummcqQuantitative AptitudeCompetitive Exam2026
A and B can complete a work in days and days respectively. Both work for days and then A leaves. Find how much time will B take to complete the remaining work?
Q144mediummcqMathematicsCompetitive Exam2026
A pump can fill a tank with water in hours. Due to leakage in the bottom, it takes hours to fill it. In what time will the leak empty the fully filled tank?
Q145mediummcqQuantitative AptitudeCompetitive Exam2026
If men can build a wall of length in days, then how many men are required to build the same wall of length in days?
Q146hardmcqQuantitative AptitudeSSC Selection Post 2021 Matriculation Level2026
A, B and C can do of a work in days, days and days, respectively. They began the work together but A left days before the completion of the work. In how many days was the work completed?
Q147mediummcqQuantitative AptitudePractice Test2026
A reservoir can be completely filled in by an inlet pipe. A leakage pipe can empty the full reservoir in . If both pipes are opened together, find the time required to fill the reservoir.
Q148mediummcqQuantitative AptitudePractice Test2026
or can build a wall of in . How many days will and take to build a wall of ?
Q149mediummcqQuantitative AptitudeCompetitive Exam2026
A can finish one-third of a work in 5 days, and B can finish 50% of the same work in 15 days. If they work together, then in how many days will they finish 50% of the work?
Q150mediummcqQuantitative AptitudePractice Paper2026
A pump can fill a tank with water in . Due to leakage in the bottom, it takes to fill it. In what time will the leak empty the fully filled tank?
Q151mediummcqQuantitative AptitudeCompetitive Exam2026
A completes a work in 3 days while B completes it in 6 days. If they work alternately with A starting work first, then in how many days will the work be finished?
Q152mediummcqQuantitative AptitudePractice Test2026
Working per day, Yashu can copy a book in . How many hours per day should he work to finish the work in ?
Q153mediummcqQuantitative AptitudePractice Test2026
Sarthak can fill a sandpit with sand in while Vivan takes to fill it. Ali can empty all of the sand from a filled sandpit in . If all three start working when the pit is empty, in how many days will the sandpit be full again?
Q154mediummcqQuantitative AptitudePractice Test2026
If people can complete a piece of work in days by working hours a day, then how many hours a day should people work to complete the same work in days?
Q155mediummcqQuantitative AptitudePractice Test2026
Nine pipes are attached to a tank, of which some are emptying pipes and some are filling pipes. Each filling pipe can fill the empty tank in , while each emptying pipe can empty the fully filled up tank in . If the tank is full and all the pipes are opened simultaneously, the tank is emptied after . The number of emptying pipes is:
Q156mediummcqQuantitative Aptitude@NUM: 56Competitive Exam2026
A, B and C can complete a certain work in , and days, respectively. A and B together start the work and B leaves after working for days. A and C together will complete the remaining work in ______ days.
Q157mediummcqQuantitative AptitudeCompetitive Exam2026
Akash is 3 times as good a workman as Baldev and therefore is able to finish a job in 40 days less than Baldev. Working together, they can finish it in ________.
Q158mediummcqQuantitative AptitudeCompetitive Exams2026
At a construction site, 15 men or 10 machines can construct a room in 66 days. In how many days can 5 men and 4 machines together complete the work?
Q159mediummcqQuantitative AptitudeSSC CGL2026
Painter A can paint a house in 40 days and Painter B can do it in 60 days. With the help of C, they did the job in 20 days only. Then, C alone can do the job in:
Q160easymcqQuantitative AptitudeSSC Selection Post 2021 Matriculation Level2026
A is three times more efficient than B and together they finish a piece of work in days. In how many days can A alone finish the same work?
Q161mediummcqQuantitative AptitudeCompetitive Exams2026
and can do a work in days and days, respectively. If they work for a day alternately, starting with , then in how many days will the work be completed?
Q162mediummcqQuantitative AptitudeSSC CGL2026
A can do a certain work in 40 days. B is 60% more efficient than A. Both work together for 10 days. C alone completes the remaining work in 10
2
1

days. Working together, B and C can complete 44% of the original work in:
Q163mediummcqQuantitative AptitudeCompetitive Exam2026
persons can repair a tunnel in days working hours a day. In how many days will persons working hours a day complete the work?
Q164easymcqQuantitative AptitudeCompetitive Exam2026
If 108 workers can build a wall in 36 days, then in how many days can 48 workers build the same wall?
Q165mediummcqQuantitative AptitudePractice Test2026
men can do a work in days. Find the amount of work done by men in days.
Q166mediummcqQuantitative AptitudeCompetitive Exam2026
In the first 44 overs of a cricket match, the run rate was 5.1runs/over. Calculate the required run rate in the remaining 6 overs to reach the target of 294 runs?
Q167mediummcqQuantitative AptitudeCompetitive Exam Practice2026
A and B can do a work in 15 days and 30 days, respectively. They start working together, but A leaves after 3 days. How much time will B take to complete the remaining work?
Q168mediummcqQuantitative AptitudeSSC CGL2026
A and B together can complete a work in 15 days. If A, B and C working together can complete the same work in 10 days, then in how many days can C alone complete the same work?
Q169mediummcqQuantitative AptitudePrepp2026
Arvind works times as fast as Suresh. If Suresh can complete a work in days independently, then find the number of days in which Arvind and Suresh can together finish the work.
Q170mediummcqQuantitative AptitudeCompetitive Exam2026
2 men and 1 woman together can complete a piece of work in 14 days. 4 women and 2 men together can do it in 8 days. If a man gets ₹600 per day, how much should a woman get per day?
Q171mediummcqQuantitative AptitudeCompetitive Exam2026
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take:
Q172mediummcqQuantitative AptitudeSSC CGL2026
P alone can do a piece of work in 8 days and Q alone can do the same work in 10 days. In how many days will both together complete the same work?
Q173mediummcqQuantitative AptitudeCompetitive Exam2026
If 72 boys can build a wall of length in 21 days, how many boys would take 18 days to build a similar type of wall of length ?
Q174mediummcqQuantitative AptitudeSSC GD Constable2026
In 1 day, 25 bottles are packed by Arjun, while 22 bottles are packed by Karan in the same time. They are working on alternate days such that Arjun works on the 1
st
day, Karan on 2
nd
, Arjun on 3
rd
and so on. How many bottles will be packed in 9 days?
Q175mediummcqQuantitative AptitudeSSC CGL2026
Abhay can do a work in 22 days. Nidhi is 28% more efficient than Abhay. The number of days Nidhi will take to do the same piece of work is:
Q176mediummcqQuantitative AptitudeCompetitive Exam2026
If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?
Q177mediummcqQuantitative AptitudeUP Police Constable2026
A can do a certain job in . B is more efficient than A. To do the same job, B alone would take how many days?
Q178mediummcqQuantitative AptitudeSSC CGL2026
can complete of a work in days. can complete of the same work in days and can complete of the same work in days. If and worked together for days, then find how much time (in days) will alone take to complete the remaining work?
Q179easymcqQuantitative AptitudeUP Police Constable2026
A can complete a task in days while B can complete it in days. In how many days can C complete the task if all of them together can complete it in days?
Q180mediummcqQuantitative AptitudeCompetitive Exam2026
A can do three-fourth of a work in 12 days and B can do four-fifth of the same work in 20 days. In how many days can they complete the whole work, working together?
Q181mediummcqQuantitative AptitudeCompetitive Exam2026
B & C can complete a task in days while A, B & C can complete the task in days. In how many days can A complete the task alone?
Q182mediummcqQuantitative Aptitude@NUM: 68SSC CGL2026
Working together A, B and C can complete a piece of work in days. After working together for days, C left the work. A and B completed the remaining work in days. The number of days taken by C alone to complete the same work is:
Q183mediummcqQuantitative AptitudeSSC CGL2026
A, B and C can do a piece of work in 20 days, 30 days and 60 days, respectively, working alone. How soon can the work be done if A is assisted by B and C each on every alternate day?
Q184mediummcqQuantitative AptitudeSSC GD Constable2026
A school is running a tree plantation drive to bring awareness among students about the environment. If 3 teachers can complete the work of tree plantation in 4 days and 4 students take 6 days to do the same work, then how many days will 3 teachers and 2 students take to complete the work of tree plantation?
Q185mediummcqQuantitative AptitudeUP Police Constable2026
Abhay and Shreya can individually complete a piece of work in and respectively. Starting with Abhay, they work alternately for a minute each till the work is completed, with only the one working at the end being allowed to work for less than a minute in the final turn. How long will it take the duo to complete the work?
Q186mediummcqQuantitative AptitudePractice Mock2026
Raju can complete a piece of job in 15hours, Vinay in 20hours and Vardhan in 30hours. If they work together and they are paid Rs. 7,200 for the job, then what amount would Vinay receive?
Q187mediummcqQuantitative AptitudeUP Police Constable2026
Raksha can complete a piece of work in while Esther takes to complete the work. They start working together but Raksha leaves before the work gets over. For how many days does Esther work?
Q188mediummcqQuantitative AptitudeSSC CGL2026
A labourer can do a job in 36 hours. After 9 hours he takes a break. What fraction of the job is yet to be done?
Q189mediummcqQuantitative AptitudeCompetitive Exam2026
Two workers - Sagar and Manish - are working on a heavy machine to melt waste metal. Sagar can complete the work in 15 days while both workers on alternate basis can complete the work in 12 days. In how many days can Manish alone complete the work?
Q190mediummcqQuantitative AptitudeSSC CGL2026
Two persons and can complete a task in and , respectively. They work together and leaves before the task is completed. The number of days taken to complete the whole task is:
Q191mediummcqQuantitative AptitudePractice Mock2026
P and Q can do a piece of work in 36days, Q and R can do it in 60days, and P and R can do it in 45days. When P, Q and R work together, how much work is finished by them in 5days?
Q192mediummcqQuantitative AptitudeSSC CGL2026
and together finish a task in . If alone can finish the same task in , then how many days will alone take to finish the task?
Q193mediummcqQuantitative AptitudeSSC Selection Post 2021 Matriculation Level2026
There are three inlet pipes X, Y and Z in a tank. X and Y can fill the tank in hours. Y and Z can fill the tank in hours. Z and X can fill the tank in hours. The number of hours in which all the three pipes can fill the tank, if operated simultaneously, is:
Q194mediummcqQuantitative AptitudeCompetitive Exam2026
A single person takes minutes to fill a bottle. If from 11 am to 12.30 pm bottles are to be filled, how many persons should be employed on this job?
Q195mediummcqQuantitative AptitudeCompetitive Exam2026
A machine can complete double the work that a man can complete in a given period of time. To complete a work, 10 machines and 5 men take 60 days. If there were 10 men and 5 machines, then the time it would have taken to complete the work is:
Q196mediummcqQuantitative AptitudeUP Police Constable Re-Exam2026
and can do a work in and respectively. They worked together for and then left. In how many days did finish the remaining work?
Q197mediummcqMathematicsCompetitive Exam2026
How many workers would be needed to complete the same task in days if it takes days for workers to complete a task?
Q198mediummcqQuantitative AptitudePractice Paper2026
A work is done by in and the same work is done by in . If and work together, then they will complete the work in how many days?
Q199mediummcqQuantitative AptitudeCompetitive Exam2026
A and B can do a piece of work separately in 10 days and 8 days, respectively. If they work alternately and A begins the work, in how many days will the work be completed?
Q200mediummcqQuantitative AptitudeSSC Competitive Exams2026
A group of men decided to complete a job in 4 days. However, since 10 men dropped out every day, the job got completed at the end of the 7th day. How many men were there in the beginning?

Frequently Asked Questions

How many Time And Work questions are on ExamTest.live?
We have 227 Time And Work questions spread across 3 pages, covering easy, medium, and hard difficulty levels with detailed explanations.
Are Time And Work MCQs free?
Yes. All Time And Work questions, answers, and explanations on ExamTest.live are completely free. No account or subscription required.
Which exams include Time And Work questions?
Time And Work questions are commonly asked in Quantitative Aptitude, Mathematics, Quantitative Aptitude@NUM: 70, Quantitative Aptitude@NUM: 56, Quantitative Aptitude@NUM: 68. You can filter by exam using the links above.
How do I practice Time And Work questions effectively?
Start with easy questions to build confidence, then tackle medium and hard ones. Use the filter buttons to sort by difficulty. Reveal the answer only after attempting each question, and read the explanation thoroughly.