X and Y can complete a work in 12 days and 18 days respectively. They started doing the work together but after 4 days Y had to leave and X alone completed the remaining work. In how many days was the whole work completed?
Eight labourers working 10 hours a day completed a work in 18 days. If only 5 labourers are working, then in how many hours a day should they work to finish the work in 24 days?
A contractor undertakes to make a tunnel in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?
Q104mediummcqQuantitative AptitudeSSC CGL2026
Pannalal has done 3 1 rd of a job in 20 days, Saiprasad completes the rest of the job in 10 days. In how many days can they together do the job?
A frog was at the bottom of an 80m deep well. It attempted to come out of it by jumping. In each jump, it covered 1.15m but slipped down by 0.75m. The number of jumps after which it would be out of the well is:
Pipes A and B can fill a tank in 16 hours and 24 hours, respectively, whereas pipe C alone can empty the full tank in x hours. When all the 3 pipes are opened together, the tank is full in 2074 hours. What is the value of x?
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3:2. In how many days can the faster person complete the job?
Q110mediummcqQuantitative AptitudeSSC CGL2026
Prabodh has done 1/2 of a job in 30 days, Sapan completes the rest of the job in 45 days. In how many days can they together do the job?
A takes 50% more time to complete a work than B. If together they take 27 days to complete the work, how much time shall B take to do it alone?
Q112mediummcqQuantitative AptitudeSSC CGL2026
The ratio of efficiencies of A and B for doing a certain work is 5:8. Working together they can complete the work in 20 days. A alone will complete 25% of that work in:
A is half as efficient as B who is thrice as efficient as C. In how many days can all 3 of them complete a task if B can complete the task alone in 6 days?
Q114mediummcqQuantitative AptitudeSSC CGL2026
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?
Q115mediummcqMathematicsCompetitive Exam2026
Komal can do a work in 51 days. Bimal is 50% more efficient than Komal in doing the work. In how many days Bimal will do that work?
A and B each can do a work in 75 days. They began the work together but A left after some time and B completed the remaining work in 23 days. After how many days of the start of the work did A leave?
Q117hardmcqQuantitative AptitudeSSC Selection Post 2021 Matriculation Level2026
A tap can fill a tank in 6 hours. After 4 hours it was found that only 60% of the tank is full due to a leakage at the bottom which was then immediately repaired. In how much time will the tank be completely filled?
A and B can complete a piece of work in 25 days and 55 days, respectively. The total number of days (in whole number) to complete the work, if A and B both work together, is:
A can do 53th of a work in 12 days, and B can do 31rd of that work in 15 days. They worked together for 12 days and then A left the work. B alone will complete the remaining work in how many days?
A and B can complete a task in 12 days, B and C can complete the task in 16 days, A and C can complete the task in 24 days. In how many days will they together complete the task?
A and B complete a work in 12 and 15 days, respectively. They started the work alternatively for 1 day each and A started the work first. In how much time will 60% of the work be completed?
Q123mediummcqQuantitative AptitudeSSC CGL2026
P and Q can do a project in 25 and 50 days respectively. In how many days can they complete 18% of the project if they work together?
Anita and Anand can complete a work in 12 days and 18 days respectively. They undertook to complete that work for ₹48,000. With the help of Arun, they completed the work in 6 days. Find the sum of the shares of Anita and Anand (in ₹).
Q125easymcqQuantitative AptitudeSSC CGL2026
A group of 25 tourists consume 5 containers of food in 8 days in a hotel. How many containers will be required for 10 tourists to eat for 16 days?
A can complete 40% of a work in 6 days and B can complete 33 3 1 % of the same work in 8 days. They work together for 8 days. C alone completes the remaining work in 4 days. A and C together will complete the same work in:
Q127mediummcqQuantitative AptitudeAdda2472026
If 72 boys can build a wall of 280m length in 21 days, how many boys would take 18 days to build a similar type of wall of length 200m?
Aman and Rajan are working at a construction site. In some engineering experiment, Aman is constructing a wall, while Rajan is demolishing that wall. Aman can completely build the wall in 15 days, while Rajan will take 20 days to completely demolish the wall. In how many days will the complete wall be built for the first time if they work on alternate days, with Aman working on the 1 st day?
A can complete 25% of the work in 4 days, B can complete 50% of the same work in 12 days and C can complete the same work in 32 days. They started working together but C left after 4 days of the start and A left 6 days before the completion of the work. In how many days was the work completed?
In a military camp, there was sufficient food for 190 days for a total of 4000 men. After 30 days, 800 men left the camp. The remaining men will spend the remaining food provisions in how many days?
A can do three-seventh of a work in 15 days and B can do two-fifth of the same work in 14 days. If A and B work together, then how long (in days) will they take to complete the work?
A takes 84 hours to finish a work. B completes the same work in one-fourth of the time taken by A. What fraction of work will they complete in 12 hours?
A can finish a work in 15 days and B can do the same work in twice the time taken by A. Then, working together, what part of the same work they can finish in five days?
A and B each can do a work in 75 days. They began the work together but A left after some time and B completed the remaining work in 23 days. After how many days of the start of the work did A leave?
Pipes A and B can fill a tank in 18 hours and 27 hours, respectively, whereas pipe C can empty the full tank in 54 hours. All three pipes are opened together, but pipe C is closed after 12 hours. In how much time (in minutes) will the one-third of the remaining part of the tank be filled by A and B together?
4 men and 4 women can complete a work in 5 days, while 2 men and 5 women can finish it in 6 days. How much time (in days) will be taken by 1 woman working alone and 1 man working all by himself to complete the work, respectively?
3 men can finish a work in 10 days, 4 women can finish it in 12 days and 10 qualified workers can finish it in 6 days. In how many days is the work finished by 4 men, 4 women and 4 qualified workers, working together every day?
Manav and Manu can complete a piece of work in 16 days and 24 days, respectively. They worked together for 8 days, after which Manav leaves. In how many days can Manu finish the remaining work?
Three pipes can fill a tank in 15 hours, 12 hours and 10 hours, respectively. If all the three pipes are opened simultaneously for 3 hours, then what percentage of the tank will remain unfilled?
A and B can complete a work in 16 days and 12 days respectively. Both work for 4 days and then A leaves. Find how much time will B take to complete the remaining work?
Q144mediummcqMathematicsCompetitive Exam2026
A pump can fill a tank with water in 3 hours. Due to leakage in the bottom, it takes 321 hours to fill it. In what time will the leak empty the fully filled tank?
If 45 men can build a wall of 360m length in 18 days, then how many men are required to build the same wall of 180m length in 15 days?
Q146hardmcqQuantitative AptitudeSSC Selection Post 2021 Matriculation Level2026
A, B and C can do 50% of a work in 15 days, 12 days and 20 days, respectively. They began the work together but A left 2 days before the completion of the work. In how many days was the work completed?
A reservoir can be completely filled in 18hours by an inlet pipe. A leakage pipe can empty the full reservoir in 36hours. If both pipes are opened together, find the time required to fill the reservoir.
A can finish one-third of a work in 5 days, and B can finish 50% of the same work in 15 days. If they work together, then in how many days will they finish 50% of the work?
A pump can fill a tank with water in 3hours. Due to leakage in the bottom, it takes 321hours to fill it. In what time will the leak empty the fully filled tank?
A completes a work in 3 days while B completes it in 6 days. If they work alternately with A starting work first, then in how many days will the work be finished?
Sarthak can fill a sandpit with sand in 14days while Vivan takes 35days to fill it. Ali can empty all of the sand from a filled sandpit in 12days. If all three start working when the pit is empty, in how many days will the sandpit be full again?
If 64 people can complete a piece of work in 8 days by working 12 hours a day, then how many hours a day should 32 people work to complete the same work in 15 days?
Nine pipes are attached to a tank, of which some are emptying pipes and some are filling pipes. Each filling pipe can fill the empty tank in 24hours, while each emptying pipe can empty the fully filled up tank in 18hours. If the tank is full and all the pipes are opened simultaneously, the tank is emptied after 9hours. The number of emptying pipes is:
A, B and C can complete a certain work in 12, 15 and 20 days, respectively. A and B together start the work and B leaves after working for 4 days. A and C together will complete the remaining work in ______ days.
Akash is 3 times as good a workman as Baldev and therefore is able to finish a job in 40 days less than Baldev. Working together, they can finish it in ________.
At a construction site, 15 men or 10 machines can construct a room in 66 days. In how many days can 5 men and 4 machines together complete the work?
Q159mediummcqQuantitative AptitudeSSC CGL2026
Painter A can paint a house in 40 days and Painter B can do it in 60 days. With the help of C, they did the job in 20 days only. Then, C alone can do the job in:
Q160easymcqQuantitative AptitudeSSC Selection Post 2021 Matriculation Level2026
A is three times more efficient than B and together they finish a piece of work in 30 days. In how many days can A alone finish the same work?
A and B can do a work in 13 days and 26 days, respectively. If they work for a day alternately, starting with A, then in how many days will the work be completed?
Q162mediummcqQuantitative AptitudeSSC CGL2026
A can do a certain work in 40 days. B is 60% more efficient than A. Both work together for 10 days. C alone completes the remaining work in 10 2 1 days. Working together, B and C can complete 44% of the original work in:
In the first 44 overs of a cricket match, the run rate was 5.1runs/over. Calculate the required run rate in the remaining 6 overs to reach the target of 294 runs?
A and B can do a work in 15 days and 30 days, respectively. They start working together, but A leaves after 3 days. How much time will B take to complete the remaining work?
Q168mediummcqQuantitative AptitudeSSC CGL2026
A and B together can complete a work in 15 days. If A, B and C working together can complete the same work in 10 days, then in how many days can C alone complete the same work?
Q169mediummcqQuantitative AptitudePrepp2026
Arvind works 4 times as fast as Suresh. If Suresh can complete a work in 20 days independently, then find the number of days in which Arvind and Suresh can together finish the work.
2 men and 1 woman together can complete a piece of work in 14 days. 4 women and 2 men together can do it in 8 days. If a man gets ₹600 per day, how much should a woman get per day?
In 1 day, 25 bottles are packed by Arjun, while 22 bottles are packed by Karan in the same time. They are working on alternate days such that Arjun works on the 1 st day, Karan on 2 nd , Arjun on 3 rd and so on. How many bottles will be packed in 9 days?
Q175mediummcqQuantitative AptitudeSSC CGL2026
Abhay can do a work in 22 days. Nidhi is 28% more efficient than Abhay. The number of days Nidhi will take to do the same piece of work is:
A can do a certain job in 120 days. B is 60% more efficient than A. To do the same job, B alone would take how many days?
Q178mediummcqQuantitative AptitudeSSC CGL2026
A can complete 32 of a work in 8 days. B can complete 53 of the same work in 12 days and C can complete 94 of the same work in 8 days. If A and B worked together for 5 days, then find how much time (in days) will C alone take to complete the remaining work?
A can complete a task in 8 days while B can complete it in 12 days. In how many days can C complete the task if all 3 of them together can complete it in 3 days?
A can do three-fourth of a work in 12 days and B can do four-fifth of the same work in 20 days. In how many days can they complete the whole work, working together?
Working together A, B and C can complete a piece of work in 24 days. After working together for 4 days, C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:
Q183mediummcqQuantitative AptitudeSSC CGL2026
A, B and C can do a piece of work in 20 days, 30 days and 60 days, respectively, working alone. How soon can the work be done if A is assisted by B and C each on every alternate day?
A school is running a tree plantation drive to bring awareness among students about the environment. If 3 teachers can complete the work of tree plantation in 4 days and 4 students take 6 days to do the same work, then how many days will 3 teachers and 2 students take to complete the work of tree plantation?
Abhay and Shreya can individually complete a piece of work in 42 mins and 70 mins respectively. Starting with Abhay, they work alternately for a minute each till the work is completed, with only the one working at the end being allowed to work for less than a minute in the final turn. How long will it take the duo to complete the work?
Raju can complete a piece of job in 15hours, Vinay in 20hours and Vardhan in 30hours. If they work together and they are paid Rs. 7,200 for the job, then what amount would Vinay receive?
Raksha can complete a piece of work in 12 days while Esther takes 20 days to complete the work. They start working together but Raksha leaves 4 days before the work gets over. For how many days does Esther work?
Q188mediummcqQuantitative AptitudeSSC CGL2026
A labourer can do a job in 36 hours. After 9 hours he takes a break. What fraction of the job is yet to be done?
Two workers - Sagar and Manish - are working on a heavy machine to melt waste metal. Sagar can complete the work in 15 days while both workers on alternate basis can complete the work in 12 days. In how many days can Manish alone complete the work?
Q190mediummcqQuantitative AptitudeSSC CGL2026
Two persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed. The number of days taken to complete the whole task is:
P and Q can do a piece of work in 36days, Q and R can do it in 60days, and P and R can do it in 45days. When P, Q and R work together, how much work is finished by them in 5days?
Q192mediummcqQuantitative AptitudeSSC CGL2026
X and Y together finish a task in 12 days. If Y alone can finish the same task in 15 days, then how many days will X alone take to finish the task?
Q193mediummcqQuantitative AptitudeSSC Selection Post 2021 Matriculation Level2026
There are three inlet pipes X, Y and Z in a tank. X and Y can fill the tank in 45 hours. Y and Z can fill the tank in 36 hours. Z and X can fill the tank in 72 hours. The number of hours in which all the three pipes can fill the tank, if operated simultaneously, is:
A single person takes 6 minutes to fill a bottle. If from 11 am to 12.30 pm 1845 bottles are to be filled, how many persons should be employed on this job?
A machine can complete double the work that a man can complete in a given period of time. To complete a work, 10 machines and 5 men take 60 days. If there were 10 men and 5 machines, then the time it would have taken to complete the work is:
C and B can do a work in 18 days and 24 days respectively. They worked together for 8 days and then C left. In how many days did B finish the remaining work?
Q197mediummcqMathematicsCompetitive Exam2026
How many workers would be needed to complete the same task in 6 days if it takes 10 days for 15 workers to complete a task?
A work is done by 3 males in 16 days and the same work is done by 6 females in 16 days. If 12 males and 8 females work together, then they will complete the work in how many days?
A and B can do a piece of work separately in 10 days and 8 days, respectively. If they work alternately and A begins the work, in how many days will the work be completed?
A group of men decided to complete a job in 4 days. However, since 10 men dropped out every day, the job got completed at the end of the 7th day. How many men were there in the beginning?
How many Time And Work questions are on ExamTest.live?▼
We have 227 Time And Work questions spread across 3 pages, covering easy, medium, and hard difficulty levels with detailed explanations.
Are Time And Work MCQs free?▼
Yes. All Time And Work questions, answers, and explanations on ExamTest.live are completely free. No account or subscription required.
Which exams include Time And Work questions?▼
Time And Work questions are commonly asked in Quantitative Aptitude, Mathematics, Quantitative Aptitude@NUM: 70, Quantitative Aptitude@NUM: 56, Quantitative Aptitude@NUM: 68. You can filter by exam using the links above.
How do I practice Time And Work questions effectively?▼
Start with easy questions to build confidence, then tackle medium and hard ones. Use the filter buttons to sort by difficulty. Reveal the answer only after attempting each question, and read the explanation thoroughly.